Signature by Peridot, Andheri West
Lapsed
by Lotus Builders And Developers · Andheri West, Mumbai 400053 · Map
- Launched
- Jun 20223 yrs 6 mths promised
- Possession (MahaRERA)
- Dec 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 58 of 9462%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 74
- 2 BHK
- 20
- Total units
- 94
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 70% | 58 | |
| 100% | 100% | 70% | – | |
| 100% | 100% | 70% | – | |
| 100% | 100% | 30% | 58 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400053
Projects with 40–200 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 6 mths | 4 yrs 2 mths |
| Possession date extended | No | 1 of 3 |
| Possession date (MahaRERA) | Dec 2025 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 62% | 81% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Paranjape Aspire, Andheri West
- Codename Rare By Runwal, Andheri West
- Mdm Maestro, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Paranjape Aspire | June 2022 | March 2027 | 61% | 73 units booked out of 90 units for sale |
| Codename Rare By Runwal | April 2022 | June 2026 | 100% | 66 units booked out of total 68 units |
| Mdm Maestro | January 2023 | December 2026 | 100% | 13 units booked out of 23 units for sale |
About this project
Signature by Peridot by Lotus Builders And Developers is a 94-unit MHADA-sanctioned project in Andheri West, Mumbai 400053, launched in June 2022; its MahaRERA registration has lapsed. 58 units booked out of total 94 units. The concrete structure (RCC) is complete.
Read full summary
Signature by Peridot is a MHADA-sanctioned project by Lotus Builders And Developers in Andheri West, Mumbai 400053, registered with MahaRERA as P51800046020. It was launched in June 2022. It has 94 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.
58 units booked out of total 94 units (62%).