The New Anand Deep Chs Ltd, Mulund West

Lapsed

by Shreejee Buildcon · Mulund West, Mumbai 400080 · Map

Launched
Dec 20223 yrs 9 mths promised
Possession (MahaRERA)
Sep 2026Not extendedWhat does Lapsed mean?
Concrete structure
95%Mid-construction
Booked (free sale)
28 of 28100% · 28 rehab units
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale28 booked out of 28 units

Rehab28 units for existing members

Total 56 units. Rehab units are not for sale.

Project facts

1 BHK
12
2 BHK
16
3 BHK
25
Other units
3
Total units
56
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
28
Rehab units
28
Reserved units
27

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)95%
Finishes, lifts and services25%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 5%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 70%Oct 2026: Concrete structure (RCC) 95%Dec 2024: Final finishes 18%Dec 2025: Final finishes 18%Jul 2026: Final finishes 18%Oct 2026: Final finishes 25%Excavation 100%Concrete structure (RCC) 95%Final finishes 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%25%28
100%70%18%28
100%70%18%28
100%5%18%36

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths3 yrs 6 mths
Possession date extendedNo3 of 6
Possession date (MahaRERA)Sep 2026Dec 2026
Concrete structure (RCC)95%59%
Units booked (free sale)100%79%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

The New Anand Deep Chs Ltd by Shreejee Buildcon is a 56-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in December 2022; its MahaRERA registration has lapsed. 28 units booked out of 28 units for sale. The concrete structure (RCC) is 95% complete.

Read full summary

The New Anand Deep Chs Ltd is an SRA-sanctioned project by Shreejee Buildcon in Mulund West, Mumbai 400080, registered with MahaRERA as P51800048097. It was launched in December 2022. It has 56 units in 2 buildings: 53 homes (1, 2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 56 units, 28 are for sale and 28 are rehab units for existing members.

Possession was due in September 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 95% complete, final finishes 25% complete.

28 units booked out of 28 units for sale (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 70% to 95%.