Rock Highland, Kandivali West
by Rock Estates · Kandivali West, Mumbai 400067 · Map
- Launched
- Feb 20233 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 15%Mid-construction
- Booked
- 146 of 19376% · 105 in Jul 2026
- Buildings
- 10.5 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 5
- 1 BHK
- 2
- 2 BHK
- 114
- 3 BHK
- 72
- Total units
- 193
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 15% | 0% | 146 | |
| 100% | 0% | 0% | 105 | |
| 100% | 0% | 0% | 13 | |
| 100% | 0% | 0% | 17 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 90–400 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 10 mths | 4 yrs 10 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2027 |
| Concrete structure (RCC) | 15% | 49% |
| Units booked | 76% | 52% |
| MahaRERA complaints (filed by or against the builder) | 2 | 0 |
The 6 projects
- Charkop Nandanvan Chsl, Kandivali West
- Jaswanti Jewel, Kandivali West
- Goyal Aspire, Kandivali West
- Shraddha Gold Crest, Kandivali West
- LA SERENA Tower 5, Tower 6 and Tower 7, Kandivali West
- ShreejiAikyam, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Charkop Nandanvan Chsl | March 2023 | December 2026 | 23% | 136 units booked out of 145 units for sale |
| Jaswanti Jewel | January 2023 | December 2027 | 100% | 60 units booked out of total 129 units |
| Goyal Aspire | January 2023 | October 2026 | 100% | 61 units booked out of 68 units for sale |
| Shraddha Gold Crest | March 2023 | December 2027 | 22% | 26 units booked out of total 129 units |
| LA SERENA Tower 5, Tower 6 and Tower 7 | April 2023 | December 2028 | 75% | 84 units booked out of total 165 units |
| ShreejiAikyam | June 2023 | December 2028 | 0% | 220 units booked out of 413 units for sale |
About this project
Rock Highland by Rock Estates is a 193-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in February 2023 with possession due in December 2026. 146 units booked out of total 193 units. The concrete structure (RCC) is 15% complete.
Read full summary
Rock Highland is a BMC-sanctioned project by Rock Estates in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800049632. It was launched in February 2023. It has 193 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 15% complete, final finishes not started.
146 units booked out of total 193 units (76%). Since the July 2026 update, 41 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 15%.