Charkop Nandanvan Chsl, Kandivali West
by Jadeite Developers LLP · Kandivali West, Mumbai 400067 · Map
- Launched
- Mar 20233 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 23%Mid-construction
- Booked (free sale)
- 136 of 14594% · 43 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale136 booked out of 145 units
Rehab43 units for existing members
Total 188 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 139
- 2 BHK
- 45
- Other units
- 4
- Total units
- 188
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 145
- Rehab units
- 43
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 23% | 90% | 136 | |
| 100% | 23% | 90% | 137 | |
| 100% | 22% | 0% | 134 | |
| 100% | 13% | 0% | 69 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 90–400 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 9 mths | 4 yrs 4 mths |
| Possession date extended | No | 2 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2027 |
| Concrete structure (RCC) | 23% | 48% |
| Units booked (free sale) | 94% | 49% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 6 projects
- Shraddha Gold Crest, Kandivali West
- Rock Highland, Kandivali West
- LA SERENA Tower 5, Tower 6 and Tower 7, Kandivali West
- Sai Divine, Kandivali West
- Jaswanti Jewel, Kandivali West
- Goyal Aspire, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shraddha Gold Crest | March 2023 | December 2027 | 22% | 26 units booked out of total 129 units |
| Rock Highland | February 2023 | December 2026 | 15% | 146 units booked out of total 193 units |
| LA SERENA Tower 5, Tower 6 and Tower 7 | April 2023 | December 2028 | 75% | 84 units booked out of total 165 units |
| Sai Divine | May 2023 | Dec 2027 | 20% | 47 units booked out of 119 units for sale |
| Jaswanti Jewel | January 2023 | December 2027 | 100% | 60 units booked out of total 129 units |
| Goyal Aspire | January 2023 | October 2026 | 100% | 61 units booked out of 68 units for sale |
About this project
Charkop Nandanvan Chsl by Jadeite Developers LLP is a 188-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in March 2023 with possession due in December 2026. 136 units booked out of 145 units for sale. The concrete structure (RCC) is 23% complete.
Read full summary
Charkop Nandanvan Chsl is a MHADA-sanctioned project by Jadeite Developers LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800050125. It was launched in March 2023. It has 188 units in 1 building: 184 homes (1 and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 188 units, 145 are for sale and 43 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 23% complete, final finishes 90% complete.
136 units booked out of 145 units for sale (94%).