LA SERENA Tower 5, Tower 6 and Tower 7, Kandivali West

by Pebble Park Developers LLP · Kandivali West, Mumbai 400067 · Map

Launched
Apr 20235 yrs 8 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
75%Mid-construction
Booked
84 of 16551% · 77 in Jul 2026
Buildings
32.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
66
3 BHK
66
4 BHK
33
Total units
165
Buildings
3
Land
2.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)75%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 5%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 75%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 75%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%0%84
100%60%0%77
100%10%0%65
100%5%0%52

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 8 mths3 yrs 10 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2028Jun 2027
Concrete structure (RCC)75%21%
Units booked51%64%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

LA SERENA Tower 5, Tower 6 and Tower 7 by Pebble Park Developers LLP is a 165-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in April 2023 with possession due in December 2028. 84 units booked out of total 165 units. The concrete structure (RCC) is 75% complete.

Read full summary

LA SERENA Tower 5, Tower 6 and Tower 7 is a BMC-sanctioned project by Pebble Park Developers LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800050593. It was launched in April 2023. It has 165 units in 3 buildings, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 75% complete, final finishes not started.

84 units booked out of total 165 units (51%). Since the July 2026 update, 7 more units have been booked and the reported concrete structure (RCC) has gone from 60% to 75%.