Luxury Chsl Ltd, Goregaon West

Ready to moveLapsed

by Laxmidevi Developers · Goregaon West, Mumbai 400104 · Map

Launched
Apr 20232 yrs 2 mths originally promised
Possession (MahaRERA)
Sep 2026Extended by 1 yr 3 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
57 of 57100% · 8 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale57 booked out of 57 units

Rehab8 units for existing members

Total 65 units. Rehab units are not for sale.

Project facts

1 BHK
19
2 BHK
40
4 BHK
6
Total units
65
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
57
Rehab units
8

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 25%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%57
100%100%25%57
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400104

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400104
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 2 mths3 yrs 6 mths
Possession date extendedBy 1 yr 3 mths0 of 6
Possession date (MahaRERA)Sep 2026Nov 2026
Concrete structure (RCC)100%100%
Units booked (free sale)100%80%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Luxury Chsl Ltd by Laxmidevi Developers is a 65-unit MHADA-sanctioned project in Goregaon West, Mumbai 400104, launched in April 2023; its MahaRERA registration has lapsed. 57 units booked out of 57 units for sale. The concrete structure (RCC) is complete.

Read full summary

Luxury Chsl Ltd is a MHADA-sanctioned project by Laxmidevi Developers in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800050568. It was launched in April 2023. It has 65 units in 1 building, with 1, 2 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 65 units, 57 are for sale and 8 are rehab units for existing members.

Possession was due in September 2026, after an extension of 1 year 3 months from the original June 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

57 units booked out of 57 units for sale (100%).