Puri SeleQt, Andheri East

by Sunil Manoharlal Puri · Andheri East, Mumbai 400069 · Map

Launched
Mar 20232 yrs 9 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
85%Mid-construction
Booked (free sale)
144 of 15394% · 30 rehab units
Buildings
10.8 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale144 booked out of 153 units

Rehab30 units for existing members

Total 183 units. Rehab units are not for sale.

Project facts

2 BHK
69
3 BHK
50
4 BHK
10
5+ BHK
1
Other units
53
Total units
183
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
4
Free-sale units
153
Rehab units
30

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)85%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 85%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 25%Dec 2025: Concrete structure (RCC) 85%Jul 2026: Concrete structure (RCC) 85%Oct 2026: Concrete structure (RCC) 85%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 85%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%0%144
100%85%0%144
100%85%0%144
85%25%0%3

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400069

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400069
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 9 mths3 yrs 6 mths
Possession date extendedBy 1 yr2 of 5
Possession date (MahaRERA)Dec 2026Dec 2026
Concrete structure (RCC)85%100%
Units booked (free sale)94%46%
MahaRERA complaints (filed by or against the builder)40

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Puri SeleQt by Sunil Manoharlal Puri is a 183-unit SRA-sanctioned project in Andheri East, Mumbai 400069, launched in March 2023 with possession due in December 2026. 144 units booked out of 153 units for sale. The concrete structure (RCC) is 85% complete.

Read full summary

Puri SeleQt is an SRA-sanctioned project by Sunil Manoharlal Puri in Andheri East, Mumbai 400069, registered with MahaRERA as P51800049868. It was launched in March 2023. It has 183 units in 1 building: 130 homes (2, 3, 4 and 5+ BHK) and 53 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 183 units, 153 are for sale and 30 are rehab units for existing members.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) 85% complete, final finishes not started.

144 units booked out of 153 units for sale (94%).