Acenza, Andheri East

by Lodha Developers Limited · Andheri East, Mumbai 400069 · Map

Launched
Jan 2023First of 3 phases
Possession (MahaRERA)
May 2027 – Dec 2029Extended in 1 of 3 phases
Concrete structure
44%Weighted across 3 phases
Booked
110 of 24146% · 108 in Jul 2026
Buildings
47.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
19
2 BHK
2
3 BHK
105
4 BHK
96
5+ BHK
5
Other units
14
Total units
241
Buildings
4
Land
7.6 acres
Phases
3
MahaRERA complaints
0

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Acenza Tower A and B
Mid-construction
P5180004886211333%61%
Acenza Tower C
Nearing possession
P5180005241763100%55%
Acenza-Tower D
Early stage
PR1180002600659510%0%
Show updates by phase

Acenza Tower A and B (P51800048862)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
70%33%0%73
0%0%0%71
0%0%0%71
70%33%0%68

"–" means MahaRERA shows no figure for that update.

Acenza Tower C (P51800052417)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%70%37
100%100%23%37
100%100%0%26
100%3%0%12

"–" means MahaRERA shows no figure for that update.

Acenza-Tower D (PR1180002600659)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation85%
Concrete structure (slabs)44%
Finishes, lifts and services19%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 28%Oct 2026: Excavation 85%Jul 2026: Concrete structure (RCC) 28%Oct 2026: Concrete structure (RCC) 44%Jul 2026: Final finishes 6%Oct 2026: Final finishes 19%Excavation 85%Concrete structure (RCC) 44%Final finishes 19%

How to read construction stages

Compared with 5 similar projects in PIN 400069

Projects with 100–500 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400069
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths2 yrs 10 mths
Possession date extendedYes2 of 5
Possession date (MahaRERA)May 2027 – Dec 2029Dec 2026
Concrete structure (RCC)44%100%
Units booked46%51%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Acenza by Lodha Developers Limited is a 241-unit SRA-sanctioned project in Andheri East, Mumbai 400069, registered with MahaRERA in 3 phases, with possession dates from May 2027 to December 2029. 110 units booked out of total 241 units. The concrete structure (RCC) is 44% complete.

Read full summary

Acenza is an SRA-sanctioned project by Lodha Developers Limited in Andheri East, Mumbai 400069, registered with MahaRERA as 3 phases (P51800048862, P51800052417, PR1180002600659). The first phase was launched in January 2023. Together the phases have 241 units in 4 buildings: 227 homes (1 RK, 2 BHK, 3 BHK, 4 BHK and 5+ BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. All 3 phases are active on MahaRERA.

The phases' registered possession dates run from May 2027 to December 2029; 1 of 3 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 44% complete and final finishes 19% complete. 1 of the 3 phases has its structure complete.

110 units booked out of total 241 units (46%). Since the July 2026 update, 2 more units have been booked.

Lodha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA85
Total units across these projects15,101
Completed without extending the possession date31
Completed after an extension13
Lapsed0
Under construction41
Possession date extended on the builder's application34
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Lodha projects242 (38 of 85 projects)