Acenza, Andheri East
by Lodha Developers Limited · Andheri East, Mumbai 400069 · Map
- Launched
- Jan 2023First of 3 phases
- Possession (MahaRERA)
- May 2027 – Dec 2029Extended in 1 of 3 phases
- Concrete structure
- 44%Weighted across 3 phases
- Booked
- 110 of 24146% · 108 in Jul 2026
- Buildings
- 47.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 19
- 2 BHK
- 2
- 3 BHK
- 105
- 4 BHK
- 96
- 5+ BHK
- 5
- Other units
- 14
- Total units
- 241
- Buildings
- 4
- Land
- 7.6 acres
- Phases
- 3
- MahaRERA complaints
- 0
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Acenza Tower A and B Mid-construction | P51800048862 | 113 | 33% | 61% | |
| Acenza Tower C Nearing possession | P51800052417 | 63 | 100% | 55% | |
| Acenza-Tower D Early stage | PR1180002600659 | 51 | 0% | 0% |
Show updates by phase
Acenza Tower A and B (P51800048862)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 70% | 33% | 0% | 73 | |
| 0% | 0% | 0% | 71 | |
| 0% | 0% | 0% | 71 | |
| 70% | 33% | 0% | 68 |
"–" means MahaRERA shows no figure for that update.
Acenza Tower C (P51800052417)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 70% | 37 | |
| 100% | 100% | 23% | 37 | |
| 100% | 100% | 0% | 26 | |
| 100% | 3% | 0% | 12 |
"–" means MahaRERA shows no figure for that update.
Acenza-Tower D (PR1180002600659)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 5 similar projects in PIN 400069
Projects with 100–500 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 6 mths | 2 yrs 10 mths |
| Possession date extended | Yes | 2 of 5 |
| Possession date (MahaRERA) | May 2027 – Dec 2029 | Dec 2026 |
| Concrete structure (RCC) | 44% | 100% |
| Units booked | 46% | 51% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Parleshwar Aangan, Andheri East
- Veena Synergy, Andheri East
- Puri SeleQt, Andheri East
- Nicco Residency, Andheri East
- Himalaya, Andheri East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Parleshwar Aangan | February 2023 | December 2026 | 100% | 63 units booked out of 124 units for sale |
| Veena Synergy | February 2023 | December 2026 | 100% | 171 units booked out of total 171 units |
| Puri SeleQt | March 2023 | December 2026 | 85% | 144 units booked out of 153 units for sale |
| Nicco Residency | April 2023 | December 2026 | 38% | 100 units booked out of total 275 units |
| Himalaya | October 2022 | September 2024 | 100% | 50 units booked out of total 118 units |
About this project
Acenza by Lodha Developers Limited is a 241-unit SRA-sanctioned project in Andheri East, Mumbai 400069, registered with MahaRERA in 3 phases, with possession dates from May 2027 to December 2029. 110 units booked out of total 241 units. The concrete structure (RCC) is 44% complete.
Read full summary
Acenza is an SRA-sanctioned project by Lodha Developers Limited in Andheri East, Mumbai 400069, registered with MahaRERA as 3 phases (P51800048862, P51800052417, PR1180002600659). The first phase was launched in January 2023. Together the phases have 241 units in 4 buildings: 227 homes (1 RK, 2 BHK, 3 BHK, 4 BHK and 5+ BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. All 3 phases are active on MahaRERA.
The phases' registered possession dates run from May 2027 to December 2029; 1 of 3 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 44% complete and final finishes 19% complete. 1 of the 3 phases has its structure complete.
110 units booked out of total 241 units (46%). Since the July 2026 update, 2 more units have been booked.
Lodha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 85 |
|---|---|
| Total units across these projects | 15,101 |
| Completed without extending the possession date | 31 |
| Completed after an extension | 13 |
| Lapsed | 0 |
| Under construction | 41 |
| Possession date extended on the builder's application | 34 |
| Typical time from launch to 100% structure | 5 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Lodha projects | 242 (38 of 85 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.