Sai Divine, Kandivali West
by Shreeji Developers · Kandivali West, Mumbai 400067 · Map
- Launched
- May 2023First of 2 phases
- Possession (MahaRERA)
- Dec 2027Extended in both phases
- Concrete structure
- 20%Weighted across 2 phases
- Booked (free sale)
- 47 of 11939% · 74 rehab units
- Buildings
- 30.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale47 booked out of 119 units
Rehab74 units for existing members
Total 193 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 82
- 2 BHK
- 88
- 3 BHK
- 6
- Other units
- 17
- Total units
- 193
- Buildings
- 3
- Land
- 0.3 acres
- Phases
- 2
- MahaRERA complaints
- 0
- Free-sale units
- 119
- Rehab units
- 74
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Sai Divine Mid-construction | P51800050948 | 83 | 18% | 23% | |
| Sai Divine B And C Mid-construction | P51800055152 | 93 | 21% | 25% |
Show updates by phase
Sai Divine (P51800050948)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 18% | 0% | 21 | |
| 100% | 10% | 0% | 22 | |
| 100% | 0% | 0% | 14 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Sai Divine B And C (P51800055152)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 21% | 0% | 26 | |
| 100% | 10% | 0% | 22 | |
| 100% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 6 similar projects in PIN 400067
Projects with 80–400 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 6 mths | 4 yrs 7 mths |
| Possession date extended | Yes | 0 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Feb 2028 |
| Concrete structure (RCC) | 20% | 70% |
| Units booked (free sale) | 39% | 52% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- LA SERENA Tower 5, Tower 6 and Tower 7, Kandivali West
- Charkop 1 Abhilasha Co Operative Housing Society Limited, Kandivali West
- ShreejiAikyam, Kandivali West
- Charkop Nandanvan Chsl, Kandivali West
- Arthaya, Kandivali West
- Charkop Rakesh Co. Op. Hsg. Soceity Ltd, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| LA SERENA Tower 5, Tower 6 and Tower 7 | April 2023 | December 2028 | 75% | 84 units booked out of total 165 units |
| Charkop 1 Abhilasha Co Operative Housing Society Limited | June 2023 | December 2026 | 100% | 81 units booked out of 87 units for sale |
| ShreejiAikyam | June 2023 | December 2028 | 0% | 220 units booked out of 413 units for sale |
| Charkop Nandanvan Chsl | March 2023 | December 2026 | 23% | 136 units booked out of 145 units for sale |
| Arthaya | July 2023 | April 2028 | 95% | 58 units booked out of 131 units for sale |
| Charkop Rakesh Co. Op. Hsg. Soceity Ltd | July 2023 | December 2027 | 65% | 17 units booked out of 52 units for sale |
About this project
Sai Divine by Shreeji Developers is a 193-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, registered with MahaRERA in 2 phases, with possession due in December 2027. 47 units booked out of 119 units for sale. The concrete structure (RCC) is 20% complete.
Read full summary
Sai Divine is a MHADA-sanctioned project by Shreeji Developers in Kandivali West, Mumbai 400067, registered with MahaRERA as 2 phases (P51800050948, P51800055152). The first phase was launched in May 2023. Together the phases have 193 units in 3 buildings: 176 homes (1, 2 and 3 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA. Of the 193 units, 119 are for sale and 74 are rehab units for existing members.
The registered possession date is December 2027; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 20% complete and final finishes 0% complete. Neither phase has its structure complete.
47 units booked out of 119 units for sale (39%). Since the July 2026 update, 3 more units have been booked.