Arkade Nest, Mulund West

by Arkade Developers Pvt Ltd · Mulund West, Mumbai 400080 · Map

Launched
May 20234 yrs 1 mth promised
Possession (MahaRERA)
Jun 2027Not extended
Concrete structure
79%Mid-construction
Booked
268 of 35176% · 235 in Jul 2026
Buildings
62.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
265
3 BHK
86
Total units
351
Buildings
6
Land
2.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)79%
Finishes, lifts and services24%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 94%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 35%Jul 2026: Concrete structure (RCC) 71%Oct 2026: Concrete structure (RCC) 79%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 2%Oct 2026: Final finishes 24%Excavation 100%Concrete structure (RCC) 79%Final finishes 24%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%79%24%268
100%71%2%235
100%35%0%141
94%0%0%47

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400080

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 1 mth4 yrs 6 mths
Possession date extendedNo1 of 4
Possession date (MahaRERA)Jun 2027Dec 2027
Concrete structure (RCC)79%58%
Units booked76%33%
MahaRERA complaints (filed by or against the builder)10

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Arkade Nest by Arkade Developers Pvt Ltd is a 351-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in May 2023 with possession due in June 2027. 268 units booked out of total 351 units. The concrete structure (RCC) is 79% complete.

Read full summary

Arkade Nest is a BMC-sanctioned project by Arkade Developers Pvt Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as P51800050953. It was launched in May 2023. It has 351 units in 6 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 79% complete, final finishes 24% complete.

268 units booked out of total 351 units (76%). Since the July 2026 update, 33 more units have been booked and the reported concrete structure (RCC) has gone from 71% to 79%.

Arkade's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA27
Total units across these projects3,356
Completed without extending the possession date14
Completed after an extension0
Lapsed3
Under construction10
Possession date extended on the builder's application1
Typical time from launch to 100% structure3 years 8 months
MahaRERA complaints (filed by or against the builder), all Arkade projects15 (6 of 27 projects)

See all Arkade projects →