Arkade Nest, Mulund West
by Arkade Developers Pvt Ltd · Mulund West, Mumbai 400080 · Map
- Launched
- May 20234 yrs 1 mth promised
- Possession (MahaRERA)
- Jun 2027Not extended
- Concrete structure
- 79%Mid-construction
- Booked
- 268 of 35176% · 235 in Jul 2026
- Buildings
- 62.1 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 265
- 3 BHK
- 86
- Total units
- 351
- Buildings
- 6
- Land
- 2.1 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 79% | 24% | 268 | |
| 100% | 71% | 2% | 235 | |
| 100% | 35% | 0% | 141 | |
| 94% | 0% | 0% | 47 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400080
Projects with 150–800 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 1 mth | 4 yrs 6 mths |
| Possession date extended | No | 1 of 4 |
| Possession date (MahaRERA) | Jun 2027 | Dec 2027 |
| Concrete structure (RCC) | 79% | 58% |
| Units booked | 76% | 33% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 4 projects
- Saraswati Square, Mulund West
- Saraswati Paradise, Mulund West
- Om Sai Complex, Mulund West
- Shraddha Panorama, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Saraswati Square | May 2023 | December 2027 | 85% | 51 units booked out of 117 units for sale |
| Saraswati Paradise | June 2023 | December 2027 | 100% | 156 units booked out of 179 units for sale |
| Om Sai Complex | October 2023 | December 2033 | 0% | 54 units booked out of 281 units for sale |
| Shraddha Panorama | October 2023 | December 2027 | 30% | 40 units booked out of 182 units for sale |
About this project
Arkade Nest by Arkade Developers Pvt Ltd is a 351-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in May 2023 with possession due in June 2027. 268 units booked out of total 351 units. The concrete structure (RCC) is 79% complete.
Read full summary
Arkade Nest is a BMC-sanctioned project by Arkade Developers Pvt Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as P51800050953. It was launched in May 2023. It has 351 units in 6 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 79% complete, final finishes 24% complete.
268 units booked out of total 351 units (76%). Since the July 2026 update, 33 more units have been booked and the reported concrete structure (RCC) has gone from 71% to 79%.
Arkade's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 27 |
|---|---|
| Total units across these projects | 3,356 |
| Completed without extending the possession date | 14 |
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 10 |
| Possession date extended on the builder's application | 1 |
| Typical time from launch to 100% structure | 3 years 8 months |
| MahaRERA complaints (filed by or against the builder), all Arkade projects | 15 (6 of 27 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.