Shraddha Panorama, Mulund West
by Shraddha Prime Projects Limited · Mulund West, Mumbai 400080 · Map
- Launched
- Oct 20233 yrs 2 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 1 yr
- Concrete structure
- 30%Mid-construction
- Booked (free sale)
- 40 of 18222% · 100 rehab units
- Buildings
- 20.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale40 booked out of 182 units
Rehab100 units for existing members
Total 282 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 120
- 2 BHK
- 158
- Other units
- 4
- Total units
- 282
- Buildings
- 2
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 182
- Rehab units
- 100
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 30% | 2% | 40 | |
| 100% | 30% | 2% | 39 | |
| 100% | 29% | 2% | 39 | |
| 100% | 0% | 0% | 23 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400080
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 2 mths | 5 yrs 3 mths |
| Possession date extended | By 1 yr | 0 of 4 |
| Possession date (MahaRERA) | Dec 2027 | Oct 2028 |
| Concrete structure (RCC) | 30% | 44% |
| Units booked (free sale) | 22% | 49% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Om Sai Complex, Mulund West
- Green Origin, Mulund West
- Saraswati Paradise, Mulund West
- Arkade Nest, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Om Sai Complex | October 2023 | December 2033 | 0% | 54 units booked out of 281 units for sale |
| Green Origin | August 2023 | August 2029 | 10% | 34 units booked out of total 153 units |
| Saraswati Paradise | June 2023 | December 2027 | 100% | 156 units booked out of 179 units for sale |
| Arkade Nest | May 2023 | June 2027 | 79% | 268 units booked out of total 351 units |
About this project
Shraddha Panorama by Shraddha Prime Projects Limited is a 282-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in October 2023 with possession due in December 2027. 40 units booked out of 182 units for sale. The concrete structure (RCC) is 30% complete.
Read full summary
Shraddha Panorama is an SRA-sanctioned project by Shraddha Prime Projects Limited in Mulund West, Mumbai 400080, registered with MahaRERA as P51800053318. It was launched in October 2023. It has 282 units in 2 buildings: 278 homes (1 and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 282 units, 182 are for sale and 100 are rehab units for existing members.
Its registered possession date is December 2027, extended by 1 year from the original December 2026. Construction: excavation complete, structure (RCC) 30% complete, final finishes 2% complete.
40 units booked out of 182 units for sale (22%). Since the July 2026 update, 1 more unit has been booked.
Shraddha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 53 |
|---|---|
| Total units across these projects | 9,707 |
| Completed without extending the possession date | 16 |
| Completed after an extension | 4 |
| Lapsed | 5 |
| Under construction | 28 |
| Possession date extended on the builder's application | 18 |
| Typical time from launch to 100% structure | 4 years |
| MahaRERA complaints (filed by or against the builder), all Shraddha projects | 14 (11 of 53 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.