Skip to main content

Charkop 1 Abhilasha Co Operative Housing Society Limited, Kandivali West

by Charkop (1) Abhilasha Co Operative Housing Society Limited · Kandivali West, Mumbai 400067 · Map

Launched
Jun 20233 yrs 6 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
81 of 8793% · 35 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale81 booked out of 87 units

Rehab35 units for existing members

Total 122 units. Rehab units are not for sale.

Project facts

1 BHK
78
2 BHK
40
3 BHK
4
Total units
122
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
87
Rehab units
35

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 80%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 15%Jul 2026: Final finishes 25%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%81
100%100%25%74
100%90%15%57
100%80%0%31

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 60–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths4 yrs
Possession date extendedNo3 of 6
Possession date (MahaRERA)Dec 2026Feb 2028
Concrete structure (RCC)100%82%
Units booked (free sale)93%42%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Charkop 1 Abhilasha Co Operative Housing Society Limited by Charkop (1) Abhilasha Co Operative Housing Society Limited is a 122-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in June 2023 with possession due in December 2026. 81 units booked out of 87 units for sale. The concrete structure (RCC) is complete.

Read full summary

Charkop 1 Abhilasha Co Operative Housing Society Limited is a MHADA-sanctioned project by Charkop (1) Abhilasha Co Operative Housing Society Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800051230. It was launched in June 2023. It has 122 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 122 units, 87 are for sale and 35 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.

81 units booked out of 87 units for sale (93%). Since the July 2026 update, 7 more units have been booked.