Abundanttiafull - By Bholas, Borivali East
Lapsed
by Sandeep Dalchand Jain · Borivali East, Mumbai 400066 · Map
- Launched
- Sep 20232 yrs 9 mths promised
- Possession (MahaRERA)
- Jun 2026Not extendedWhat does Lapsed mean?
- Concrete structure
- 89%Mid-construction
- Booked (free sale)
- 21 of 6035% · 50 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale21 booked out of 60 units
Rehab50 units for existing members
Total 110 units. Rehab units are not for sale.
Project facts
- 1 RK
- 6
- 1 BHK
- 40
- 2 BHK
- 26
- 3 BHK
- 4
- 5+ BHK
- 1
- Other units
- 33
- Total units
- 110
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 60
- Rehab units
- 50
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 89% | 0% | 21 | |
| 100% | 89% | 0% | 11 | |
| 100% | 89% | 0% | 8 | |
| 100% | 89% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400066
Projects with 30–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 3 yrs 2 mths |
| Possession date extended | No | 1 of 4 |
| Possession date (MahaRERA) | Jun 2026 | Dec 2026 |
| Concrete structure (RCC) | 89% | 68% |
| Units booked (free sale) | 35% | 67% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- The Grand Residences, Borivali East
- 71P, Borivali East
- Vastu Shilp, Borivali East
- Samarpan Sankalp, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| The Grand Residences | October 2023 | December 2027 | 40% | 76 units booked out of total 104 units |
| 71P | June 2023 | December 2026 | 41% | 21 units booked out of 34 units for sale |
| Vastu Shilp | May 2023 | December 2026 | 96% | 20 units booked out of 88 units for sale |
| Samarpan Sankalp | February 2024 | December 2026 | 100% | 66 units booked out of 72 units for sale |
About this project
Abundanttiafull - By Bholas by Sandeep Dalchand Jain is a 110-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in September 2023; its MahaRERA registration has lapsed. 21 units booked out of 60 units for sale. The concrete structure (RCC) is 89% complete.
Read full summary
Abundanttiafull - By Bholas is a BMC-sanctioned project by Sandeep Dalchand Jain in Borivali East, Mumbai 400066, registered with MahaRERA as P51800052704. It was launched in September 2023. It has 110 units in 1 building: 77 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 5+ BHK) and 33 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 110 units, 60 are for sale and 50 are rehab units for existing members.
Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 89% complete, final finishes not started.
21 units booked out of 60 units for sale (35%). Since the July 2026 update, 10 more units have been booked.