The Grand Residences, Borivali East

by Matrubhumi Construction Private Ltd · Borivali East, Mumbai 400066 · Map

Launched
Oct 20234 yrs 2 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
40%Mid-construction
Booked
76 of 10473%
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
23
3 BHK
27
4 BHK
27
5+ BHK
26
Other units
1
Total units
104
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)40%
Finishes, lifts and services5%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 15%Jul 2026: Concrete structure (RCC) 40%Oct 2026: Concrete structure (RCC) 40%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 5%Excavation 100%Concrete structure (RCC) 40%Final finishes 5%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%40%5%76
100%40%0%76
100%15%0%73
100%0%0%50

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400066

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 2 mths2 yrs 10 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2027Dec 2026
Concrete structure (RCC)40%92%
Units booked73%49%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

The Grand Residences by Matrubhumi Construction Private Ltd is a 104-unit SRA-sanctioned project in Borivali East, Mumbai 400066, launched in October 2023 with possession due in December 2027. 76 units booked out of total 104 units. The concrete structure (RCC) is 40% complete.

Read full summary

The Grand Residences is an SRA-sanctioned project by Matrubhumi Construction Private Ltd in Borivali East, Mumbai 400066, registered with MahaRERA as P51800053261. It was launched in October 2023. It has 104 units in 1 building: 103 homes (2, 3, 4 and 5+ BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 40% complete, final finishes 5% complete.

76 units booked out of total 104 units (73%).