Guru Ashish, Mulund East
by Shivcorp Infra (Opc) Private Limited · Mulund East, Mumbai 400081 · Map
- Launched
- Oct 20232 yrs 5 mths originally promised
- Possession (MahaRERA)
- Mar 2027Extended by 1 yr
- Concrete structure
- 92%Mid-construction
- Booked (free sale)
- 6 of 1932%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale6 booked out of 19 units
Land-owner share10 units, not for sale
Total 29 units. Land-owner units are not for sale.
Project facts
- 1 RK
- 2
- 1 BHK
- 5
- 2 BHK
- 15
- 3 BHK
- 7
- Total units
- 29
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 19
- Land-owner share (not for sale)
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 92% | 0% | 6 | |
| 100% | 92% | 0% | 6 | |
| 100% | 85% | 0% | 5 | |
| 100% | 85% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400081
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 5 mths | 2 yrs 6 mths |
| Possession date extended | By 1 yr | 1 of 4 |
| Possession date (MahaRERA) | Mar 2027 | Jan 2027 |
| Concrete structure (RCC) | 92% | 100% |
| Units booked (free sale) | 32% | 82% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Om Shankar Bhavan, Mulund East
- Shriram Niwas, Mulund East
- Shraddha Palm, Mulund East
- Ruparel Celestia, Mulund East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Om Shankar Bhavan | July 2023 | October 2025 | 100% | – |
| Shriram Niwas | February 2024 | June 2027 | 100% | 23 units booked out of 26 units for sale |
| Shraddha Palm | February 2024 | March 2027 | 96% | 7 units booked out of 34 units for sale |
| Ruparel Celestia | February 2024 | December 2026 | 100% | 56 units booked out of total 68 units |
About this project
Guru Ashish by Shivcorp Infra (Opc) Private Limited is a 29-unit BMC-sanctioned project in Mulund East, Mumbai 400081, launched in October 2023 with possession due in March 2027. 6 units booked out of 19 units for sale. The concrete structure (RCC) is 92% complete.
Read full summary
Guru Ashish is a BMC-sanctioned project by Shivcorp Infra (Opc) Private Limited in Mulund East, Mumbai 400081, registered with MahaRERA as P51800053415. It was launched in October 2023. It has 29 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 29 units, 19 are for sale and 10 are the land-owner's share, not for sale.
Its registered possession date is March 2027, extended by 1 year from the original March 2026. Construction: excavation complete, structure (RCC) 92% complete, final finishes not started.
6 units booked out of 19 units for sale (32%).