Ruparel Celestia, Mulund East
by Aadarsh Developers · Mulund East, Mumbai 400081 · Map
- Launched
- Feb 20242 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- 56 of 6882%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 31
- 2 BHK
- 27
- Other units
- 10
- Total units
- 68
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Reserved units
- 25
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 70% | 56 | |
| 100% | 100% | 40% | 56 | |
| 100% | 22% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400081
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 10 mths | 2 yrs 5 mths |
| Possession date extended | No | 3 of 5 |
| Possession date (MahaRERA) | Dec 2026 | Mar 2027 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 82% | 42% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 5 projects
- Shraddha Palm, Mulund East
- Shriram Niwas, Mulund East
- Guru Ashish, Mulund East
- Mithagar Road Ekta CHSL, Mulund East
- Om Mayuresh, Mulund East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shraddha Palm | February 2024 | March 2027 | 96% | 7 units booked out of 34 units for sale |
| Shriram Niwas | February 2024 | June 2027 | 100% | 23 units booked out of 26 units for sale |
| Guru Ashish | October 2023 | March 2027 | 92% | 6 units booked out of 19 units for sale |
| Mithagar Road Ekta CHSL | September 2023 | December 2026 | 100% | 20 units booked out of 48 units for sale |
| Om Mayuresh | September 2023 | December 2026 | 100% | 36 units booked out of 66 units for sale |
About this project
Ruparel Celestia by Aadarsh Developers (Ruparel) is a 68-unit SRA-sanctioned project in Mulund East, Mumbai 400081, launched in February 2024 with possession due in December 2026. 56 units booked out of total 68 units. The concrete structure (RCC) is complete.
Read full summary
Ruparel Celestia is an SRA-sanctioned project by Aadarsh Developers in Mulund East, Mumbai 400081, registered with MahaRERA as P51800054935. It was launched in February 2024. It has 68 units in 1 building: 58 homes (1 and 2 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.
56 units booked out of total 68 units (82%).
Ruparel's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 28 |
|---|---|
| Total units across these projects | 6,570 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 1 |
| Lapsed | 12 |
| Under construction | 15 |
| Possession date extended on the builder's application | 14 |
| Typical time from launch to 100% structure | 5 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Ruparel projects | 872 (22 of 28 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.