Shraddha Palm, Mulund East
by Dharmadi Enterprises · Mulund East, Mumbai 400081 · Map
- Launched
- Feb 20242 yrs 1 mth originally promised
- Possession (MahaRERA)
- Mar 2027Extended by 1 yr
- Concrete structure
- 96%Mid-construction
- Booked (free sale)
- 7 of 3421% · 13 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale7 booked out of 34 units
Rehab13 units for existing members
Total 47 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 23
- 2 BHK
- 18
- 3 BHK
- 3
- 4 BHK
- 1
- Other units
- 2
- Total units
- 47
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 34
- Rehab units
- 13
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 96% | 0% | 7 | |
| 100% | 96% | 0% | 7 | |
| 100% | 4% | 0% | – | |
| 100% | 0% | 0% | 2 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400081
Projects with 20–90 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 1 mth | 2 yrs 8 mths |
| Possession date extended | By 1 yr | 2 of 4 |
| Possession date (MahaRERA) | Mar 2027 | Jan 2027 |
| Concrete structure (RCC) | 96% | 100% |
| Units booked (free sale) | 21% | 62% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Ruparel Celestia, Mulund East
- Shriram Niwas, Mulund East
- Guru Ashish, Mulund East
- Mithagar Road Ekta CHSL, Mulund East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ruparel Celestia | February 2024 | December 2026 | 100% | 56 units booked out of total 68 units |
| Shriram Niwas | February 2024 | June 2027 | 100% | 23 units booked out of 26 units for sale |
| Guru Ashish | October 2023 | March 2027 | 92% | 6 units booked out of 19 units for sale |
| Mithagar Road Ekta CHSL | September 2023 | December 2026 | 100% | 20 units booked out of 48 units for sale |
About this project
Shraddha Palm by Dharmadi Enterprises (Shraddha) is a 47-unit SRA-sanctioned project in Mulund East, Mumbai 400081, launched in February 2024 with possession due in March 2027. 7 units booked out of 34 units for sale. The concrete structure (RCC) is 96% complete.
Read full summary
Shraddha Palm is an SRA-sanctioned project by Dharmadi Enterprises in Mulund East, Mumbai 400081, registered with MahaRERA as P51800055034. It was launched in February 2024. It has 47 units in 1 building: 45 homes (1, 2, 3 and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 47 units, 34 are for sale and 13 are rehab units for existing members.
Its registered possession date is March 2027, extended by 1 year from the original March 2026. Construction: excavation complete, structure (RCC) 96% complete, final finishes not started.
7 units booked out of 34 units for sale (21%).
Shraddha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 53 |
|---|---|
| Total units across these projects | 9,707 |
| Completed without extending the possession date | 16 |
| Completed after an extension | 4 |
| Lapsed | 5 |
| Under construction | 28 |
| Possession date extended on the builder's application | 18 |
| Typical time from launch to 100% structure | 4 years |
| MahaRERA complaints (filed by or against the builder), all Shraddha projects | 14 (11 of 53 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.