Samarpan Sankalp, Borivali East
by Samarpan Homes & Developers · Borivali East, Mumbai 400066 · Map
- Launched
- Feb 20242 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 66 of 7292% · 53 rehab units
- Buildings
- 20.4 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale66 booked out of 72 units
Rehab53 units for existing members
Total 125 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 37
- 2 BHK
- 85
- Other units
- 3
- Total units
- 125
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 72
- Rehab units
- 53
- Reserved units
- 13
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 66 | |
| 100% | 100% | 0% | 63 | |
| 100% | 90% | 0% | 51 | |
| 100% | 50% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400066
Projects with 60–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 10 mths | 3 yrs 9 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Nov 2027 |
| Concrete structure (RCC) | 100% | 64% |
| Units booked (free sale) | 92% | 59% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 6 projects
- Balaji Heights Redevelopment Of Rajendra Nagar Om Sairam Chs Ltd, Borivali East
- Shiv Krupa, Borivali East
- Rivali Park - Stargaze, Borivali East
- Borivali Shiv Sadan CHSL, Borivali East
- The Grand Residences, Borivali East
- Abundanttiafull - By Bholas, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Balaji Heights Redevelopment Of Rajendra Nagar Om Sairam Chs Ltd | April 2024 | May 2027 | 12% | 59 units booked out of 162 units for sale |
| Shiv Krupa | May 2024 | December 2028 | 25% | 39 units booked out of 80 units for sale |
| Rivali Park - Stargaze | November 2023 | October 2029 | 100% | 139 units booked out of total 198 units |
| Borivali Shiv Sadan CHSL | June 2024 | October 2027 | 100% | 65 units booked out of 66 units for sale |
| The Grand Residences | October 2023 | December 2027 | 40% | 76 units booked out of total 104 units |
| Abundanttiafull - By Bholas | September 2023 | June 2026 | 89% | 21 units booked out of 60 units for sale |
About this project
Samarpan Sankalp by Samarpan Homes & Developers is a 125-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in February 2024 with possession due in December 2026. 66 units booked out of 72 units for sale. The concrete structure (RCC) is complete.
Read full summary
Samarpan Sankalp is a BMC-sanctioned project by Samarpan Homes & Developers in Borivali East, Mumbai 400066, registered with MahaRERA as P51800054977. It was launched in February 2024. It has 125 units in 2 buildings: 122 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 125 units, 72 are for sale and 53 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.
66 units booked out of 72 units for sale (92%). Since the July 2026 update, 3 more units have been booked.