Skip to main content

Gami And Jaydeep Estella, Chembur

by M/S Real Infrastructure Co · Chembur, Mumbai 400071 · Map

Launched
Feb 20243 yrs 1 mth promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
84 of 12269% · 48 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale84 booked out of 122 units

Rehab48 units for existing members

Total 170 units. Rehab units are not for sale.

Project facts

1 BHK
32
2 BHK
90
3 BHK
28
Other units
20
Total units
170
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
122
Rehab units
48

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services40%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 10%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 10%Oct 2026: Final finishes 40%Excavation 100%Concrete structure (RCC) 100%Final finishes 40%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%40%84
100%100%10%70
100%90%0%55
100%10%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 70–300 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 1 mth3 yrs 11 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Mar 2027Dec 2027
Concrete structure (RCC)100%94%
Units booked (free sale)69%71%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Gami And Jaydeep Estella by M/S Real Infrastructure Co is a 170-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in February 2024 with possession due in March 2027. 84 units booked out of 122 units for sale. The concrete structure (RCC) is complete.

Read full summary

Gami And Jaydeep Estella is a MHADA-sanctioned project by M/S Real Infrastructure Co in Chembur, Mumbai 400071, registered with MahaRERA as P51800054781. It was launched in February 2024. It has 170 units in 1 building: 150 homes (1, 2 and 3 BHK) and 20 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 170 units, 122 are for sale and 48 are rehab units for existing members.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 40% complete.

84 units booked out of 122 units for sale (69%). Since the July 2026 update, 14 more units have been booked.