Vibha Vasu, Vile Parle East

Ready to move

by R & R Developers · Vile Parle East, Mumbai 400057 · Map

Launched
Dec 20232 yrs originally promised
Possession (MahaRERA)
Feb 2027Extended by 1 yr 2 mths
Concrete structure
100%Ready to move
Booked (free sale)
16 of 16100% · 18 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale16 booked out of 16 units

Rehab18 units for existing members

Total 34 units. Rehab units are not for sale.

Project facts

2 BHK
6
3 BHK
27
4 BHK
1
Total units
34
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
16
Rehab units
18

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 54%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 90%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%16
100%100%100%16
100%100%90%13
100%54%0%2

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs3 yrs 10 mths
Possession date extendedBy 1 yr 2 mths1 of 6
Possession date (MahaRERA)Feb 2027Jun 2028
Concrete structure (RCC)100%100%
Units booked (free sale)100%66%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Vibha Vasu by R & R Developers is a 34-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in December 2023 with possession due in February 2027. 16 units booked out of 16 units for sale. The concrete structure (RCC) is complete.

Read full summary

Vibha Vasu is a BMC-sanctioned project by R & R Developers in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800053924. It was launched in December 2023. It has 34 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 34 units, 16 are for sale and 18 are rehab units for existing members.

Its registered possession date is February 2027, extended by 1 year 2 months from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

16 units booked out of 16 units for sale (100%).