Atharv Om Chandramilan, Vile Parle East
Ready to move
by Atharv Infra LLP · Vile Parle East, Mumbai 400057 · Map
- Launched
- Dec 20235 yrs promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 10 of 10100% · 34 rehab units
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale10 booked out of 10 units
Rehab34 units for existing members
Total 44 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 2 BHK
- 14
- 3 BHK
- 24
- 4 BHK
- 2
- 5+ BHK
- 3
- Total units
- 44
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 10
- Rehab units
- 34
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 10 | |
| 100% | 100% | 50% | 10 | |
| 50% | 37% | 0% | 10 | |
| 0% | 0% | 0% | 10 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400057
Projects with 20–90 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs | 2 yrs 8 mths |
| Possession date extended | No | 2 of 6 |
| Possession date (MahaRERA) | Dec 2028 | Jan 2027 |
| Concrete structure (RCC) | 100% | 80% |
| Units booked (free sale) | 100% | 61% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Vibha Vasu, Vile Parle East
- Ganesh Chhaya Co-Operative Housing Society Ltd, Vile Parle East
- Minal And Madhavkunj, Vile Parle East
- Zodiac Anjaneshwar, Vile Parle East
- Sandeep Ankur Residency, Vile Parle East
- Viva Dhanlaxmi, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vibha Vasu | December 2023 | February 2027 | 100% | 16 units booked out of 16 units for sale |
| Ganesh Chhaya Co-Operative Housing Society Ltd | December 2023 | December 2028 | 100% | 7 units booked out of 21 units for sale |
| Minal And Madhavkunj | November 2023 | December 2026 | 5% | – |
| Zodiac Anjaneshwar | January 2024 | December 2027 | 56% | 5 units booked out of 9 units for sale |
| Sandeep Ankur Residency | January 2024 | August 2026 | 60% | 10 units booked out of 13 units for sale |
| Viva Dhanlaxmi | November 2023 | August 2026 | 100% | 14 units booked out of 23 units for sale |
About this project
Atharv Om Chandramilan by Atharv Infra LLP is a 44-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in December 2023 with possession due in December 2028. 10 units booked out of 10 units for sale. The concrete structure (RCC) is complete.
Read full summary
Atharv Om Chandramilan is a BMC-sanctioned project by Atharv Infra LLP in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800054052. It was launched in December 2023. It has 44 units in 2 buildings, with 1 RK, 2 BHK, 3 BHK, 4 BHK and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 44 units, 10 are for sale and 34 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
10 units booked out of 10 units for sale (100%).