Shelton Crest, Ghatkopar East
Ready to moveLapsed
by Shelton Infrastructure Private Limited · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Nov 20231 yr 4 mths originally promised
- Possession (MahaRERA)
- Sep 2025Extended by 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 1 of 119% · 10 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 11 units
Rehab10 units for existing members
Total 21 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 9
- 3 BHK
- 9
- 4 BHK
- 2
- Other units
- 1
- Total units
- 21
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 11
- Rehab units
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 1 | |
| 100% | 100% | 90% | 1 | |
| 100% | 100% | 90% | 1 | |
| 100% | 100% | 30% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400077
Projects with 10–40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 4 mths | 3 yrs 11 mths |
| Possession date extended | By 6 mths | 0 of 5 |
| Possession date (MahaRERA) | Sep 2025 | Dec 2027 |
| Concrete structure (RCC) | 100% | 88% |
| Units booked (free sale) | 9% | 89% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Koyal Geet Chsl, Ghatkopar East
- Kush Avenuee, Ghatkopar East
- Park View, Ghatkopar East
- Sai Twin Tower, Ghatkopar East
- Rajaram Mansion, Ghatkopar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Koyal Geet Chsl | November 2023 | December 2026 | 50% | – |
| Kush Avenuee | October 2023 | April 2026 | 85% | 49 units booked out of total 58 units |
| Park View | January 2024 | December 2027 | 88% | 15 units booked out of 21 units for sale |
| Sai Twin Tower | September 2023 | December 2027 | 95% | 71 units booked out of 76 units for sale |
| Rajaram Mansion | June 2023 | December 2027 | 100% | 5 units booked out of 5 units for sale |
About this project
Shelton Crest by Shelton Infrastructure Private Limited is a 21-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in November 2023; its MahaRERA registration has lapsed. 1 unit booked out of 11 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shelton Crest is a BMC-sanctioned project by Shelton Infrastructure Private Limited in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800053697. It was launched in November 2023. It has 21 units in 1 building: 20 homes (2, 3 and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 21 units, 11 are for sale and 10 are rehab units for existing members.
Possession was due in September 2025, after an extension of 6 months from the original March 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
1 unit booked out of 11 units for sale (9%).