12 Pegasus, Bandra East
by Jayant Enterprises S N Project · Bandra East, Mumbai 400051 · Map
- Launched
- Dec 20235 yrs promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 95%Mid-construction
- Booked (free sale)
- 121 of 21856% · 292 rehab units
- Buildings
- 21.3 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale121 booked out of 218 units
Rehab292 units for existing members
Land-owner share29 units, not for sale
Total 539 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 250
- Other units
- 289
- Total units
- 539
- Buildings
- 2
- Land
- 1.3 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 218
- Rehab units
- 292
- Land-owner share (not for sale)
- 29
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 10% | 121 | |
| 100% | 82% | 0% | 118 | |
| 100% | 30% | 0% | 115 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400051
Projects with 100–500 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs | 3 yrs 5 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Dec 2028 | Jul 2027 |
| Concrete structure (RCC) | 95% | 72% |
| Units booked (free sale) | 56% | 75% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 4 projects
- Bkc 9, Bandra East
- Sajay Avenue 18, Bandra East
- Gurukrupa Nirmalam, Bandra East
- Sahakar Excel Acropolis, Bandra East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bkc 9 | January 2024 | July 2028 | 45% | 71 units booked out of 79 units for sale |
| Sajay Avenue 18 | October 2023 | August 2026 | 100% | 72 units booked out of 120 units for sale |
| Gurukrupa Nirmalam | October 2023 | December 2026 | 100% | 82 units booked out of 87 units for sale |
| Sahakar Excel Acropolis | July 2024 | Mar 2028 – Dec 2029 | 31% | 45 units booked out of 189 units for sale |
About this project
12 Pegasus by Jayant Enterprises S N Project is a 539-unit SRA-sanctioned project in Bandra East, Mumbai 400051, launched in December 2023 with possession due in December 2028. 121 units booked out of 218 units for sale. The concrete structure (RCC) is 95% complete.
Read full summary
12 Pegasus is an SRA-sanctioned project by Jayant Enterprises S N Project in Bandra East, Mumbai 400051, registered with MahaRERA as P51800054031. It was launched in December 2023. It has 539 units in 2 buildings: 250 homes (1 BHK) and 289 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 539 units, 218 are for sale, 292 are rehab units for existing members and 29 are the land-owner's share, not for sale.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 95% complete, final finishes 10% complete.
121 units booked out of 218 units for sale (56%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 82% to 95%.