Sahakar Excel Acropolis, Bandra East
by Excel Enterprises Realty LLP · Bandra East, Mumbai 400051 · Map
- Launched
- Jul 2024First of 2 phases
- Possession (MahaRERA)
- Mar 2028 – Dec 2029Not extended
- Concrete structure
- 31%Weighted across 2 phases
- Booked (free sale)
- 45 of 18924% · 99 rehab units
- Buildings
- 50.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale45 booked out of 189 units
Rehab99 units for existing members
Total 288 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 242
- 3 BHK
- 46
- Total units
- 288
- Buildings
- 5
- Land
- 0.5 acres
- Phases
- 2
- MahaRERA complaints
- 0
- Free-sale units
- 189
- Rehab units
- 99
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Sahakar excel Acropolis - I Mid-construction | P51800077177 | 180 | 50% | 16% | |
| Sahakar Excel Acropolis - II Early stage | PR1180002502764 | 108 | 0% | 16% |
Show updates by phase
Sahakar excel Acropolis - I (P51800077177)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 50% | 0% | 28 | |
| 100% | 50% | 0% | 20 | |
| 100% | 0% | 0% | 7 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Sahakar Excel Acropolis - II (PR1180002502764)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 70% | 0% | 0% | 17 | |
| 0% | 0% | 0% | 8 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 3 similar projects in PIN 400051
Projects with 100–600 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 8 mths | 4 yrs 6 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Mar 2028 – Dec 2029 | Jul 2028 |
| Concrete structure (RCC) | 31% | 95% |
| Units booked (free sale) | 24% | 60% |
| MahaRERA complaints (filed by or against the builder) | 0 | 1 |
The 3 projects
- Bkc 9, Bandra East
- 12 Pegasus, Bandra East
- Sajay Avenue 18, Bandra East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bkc 9 | January 2024 | July 2028 | 45% | 71 units booked out of 79 units for sale |
| 12 Pegasus | December 2023 | December 2028 | 95% | 121 units booked out of 218 units for sale |
| Sajay Avenue 18 | October 2023 | August 2026 | 100% | 72 units booked out of 120 units for sale |
About this project
Sahakar Excel Acropolis by Excel Enterprises Realty LLP is a 288-unit project in Bandra East, Mumbai 400051, registered with MahaRERA in 2 phases, with possession dates from March 2028 to December 2029. 45 units booked out of 189 units for sale. The concrete structure (RCC) is 31% complete.
Read full summary
Sahakar Excel Acropolis is a project by Excel Enterprises Realty LLP in Bandra East, Mumbai 400051, registered with MahaRERA as 2 phases (P51800077177, PR1180002502764). The first phase was launched in July 2024. Together the phases have 288 units in 5 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Both phases are active on MahaRERA. Of the 288 units, 189 are for sale and 99 are rehab units for existing members.
The phases' registered possession dates run from March 2028 to December 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 31% complete and final finishes 0% complete. Neither phase has its structure complete.
45 units booked out of 189 units for sale (24%). Since the July 2026 update, 17 more units have been booked.