Sajay Avenue 18, Bandra East
Lapsed
by Vinca Realtors Private Limited · Bandra East, Mumbai 400051 · Map
- Launched
- Oct 20232 yrs 10 mths promised
- Possession (MahaRERA)
- Aug 2026Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 72 of 12060% · 74 rehab units
- Buildings
- 10.5 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale72 booked out of 120 units
Rehab74 units for existing members
Total 194 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 80
- 2 BHK
- 74
- 3 BHK
- 40
- Total units
- 194
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 120
- Rehab units
- 74
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 85% | 72 | |
| 100% | 100% | 85% | 63 | |
| 100% | 28% | 0% | – | |
| 100% | 28% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400051
Projects with 90–400 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 10 mths | 4 yrs 1 mth |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Aug 2026 | May 2028 |
| Concrete structure (RCC) | 100% | 70% |
| Units booked (free sale) | 60% | 73% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 4 projects
- Gurukrupa Nirmalam, Bandra East
- 12 Pegasus, Bandra East
- Bkc 9, Bandra East
- Sahakar Excel Acropolis, Bandra East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Gurukrupa Nirmalam | October 2023 | December 2026 | 100% | 82 units booked out of 87 units for sale |
| 12 Pegasus | December 2023 | December 2028 | 95% | 121 units booked out of 218 units for sale |
| Bkc 9 | January 2024 | July 2028 | 45% | 71 units booked out of 79 units for sale |
| Sahakar Excel Acropolis | July 2024 | Mar 2028 – Dec 2029 | 31% | 45 units booked out of 189 units for sale |
About this project
Sajay Avenue 18 by Vinca Realtors Private Limited is a 194-unit MHADA-sanctioned project in Bandra East, Mumbai 400051, launched in October 2023; its MahaRERA registration has lapsed. 72 units booked out of 120 units for sale. The concrete structure (RCC) is complete.
Read full summary
Sajay Avenue 18 is a MHADA-sanctioned project by Vinca Realtors Private Limited in Bandra East, Mumbai 400051, registered with MahaRERA as P51800053190. It was launched in October 2023. It has 194 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 194 units, 120 are for sale and 74 are rehab units for existing members.
Possession was due in August 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 85% complete.
72 units booked out of 120 units for sale (60%). Since the July 2026 update, 9 more units have been booked.