Skip to main content

Bkc 9, Bandra East

by Vakratunda Buildcon Private Limited · Bandra East, Mumbai 400051 · Map

Launched
Jan 20244 yrs 6 mths promised
Possession (MahaRERA)
Jul 2028Not extended
Concrete structure
45%Mid-construction
Booked (free sale)
71 of 7990% · 54 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale71 booked out of 79 units

Rehab54 units for existing members

Total 133 units. Rehab units are not for sale.

Project facts

2 BHK
102
3 BHK
31
Total units
133
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
79
Rehab units
54

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)45%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 45%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 45%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%45%0%71
100%0%0%–
100%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400051

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400051
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 6 mths3 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jul 2028Aug 2027
Concrete structure (RCC)45%98%
Units booked (free sale)90%63%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Bkc 9 by Vakratunda Buildcon Private Limited is a 133-unit MHADA-sanctioned project in Bandra East, Mumbai 400051, launched in January 2024 with possession due in July 2028. 71 units booked out of 79 units for sale. The concrete structure (RCC) is 45% complete.

Read full summary

Bkc 9 is a MHADA-sanctioned project by Vakratunda Buildcon Private Limited in Bandra East, Mumbai 400051, registered with MahaRERA as P51800054573. It was launched in January 2024. It has 133 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 133 units, 79 are for sale and 54 are rehab units for existing members.

Its registered possession date is July 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started.

71 units booked out of 79 units for sale (90%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 45%.