Antariksh Alpha, Ghatkopar East
by Antariksh Lifespaces Private Limited · Ghatkopar East, Mumbai 400075 · Map
- Launched
- Feb 20244 yrs 4 mths promised
- Possession (MahaRERA)
- Jun 2028Not extended
- Concrete structure
- 85%Mid-construction
- Booked (free sale)
- 52 of 5988% · 40 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale52 booked out of 59 units
Rehab40 units for existing members
Total 99 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 26
- 3 BHK
- 73
- Total units
- 99
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 59
- Rehab units
- 40
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 85% | 0% | 52 | |
| 100% | 65% | 0% | 52 | |
| 100% | 0% | 0% | 35 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400075
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 4 mths | 2 yrs 8 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Jun 2028 | Mar 2027 |
| Concrete structure (RCC) | 85% | 94% |
| Units booked (free sale) | 88% | 74% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Shubham Aurum, Ghatkopar East
- Shubham Athena, Ghatkopar East
- Aakruti Solitaire, Ghatkopar East
- Divine Ultimus, Ghatkopar East
- Visava Harmony, Ghatkopar East
- Prime Vista Phase - 2, Ghatkopar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shubham Aurum | January 2024 | June 2026 | 94% | – |
| Shubham Athena | January 2024 | June 2026 | 94% | – |
| Aakruti Solitaire | May 2024 | February 2027 | 100% | 122 units booked out of 125 units for sale |
| Divine Ultimus | June 2024 | December 2027 | 90% | 40 units booked out of 54 units for sale |
| Visava Harmony | August 2024 | March 2027 | 94% | – |
| Prime Vista Phase - 2 | August 2024 | June 2028 | 0% | 51 units booked out of 77 units for sale |
About this project
Antariksh Alpha by Antariksh Lifespaces Private Limited is a 99-unit MHADA-sanctioned project in Ghatkopar East, Mumbai 400075, launched in February 2024 with possession due in June 2028. 52 units booked out of 59 units for sale. The concrete structure (RCC) is 85% complete.
Read full summary
Antariksh Alpha is a MHADA-sanctioned project by Antariksh Lifespaces Private Limited in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800055041. It was launched in February 2024. It has 99 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 99 units, 59 are for sale and 40 are rehab units for existing members.
Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 85% complete, final finishes not started.
52 units booked out of 59 units for sale (88%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 65% to 85%.