Aakruti Solitaire, Ghatkopar East
by Saptrishi Classic LLP · Ghatkopar East, Mumbai 400075 · Map
- Launched
- May 20242 yrs 9 mths promised
- Possession (MahaRERA)
- Feb 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 122 of 12598%
- Buildings
- 20.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale122 booked out of 125 units
Land-owner share30 units, not for sale
Total 155 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 91
- 2 BHK
- 63
- 3 BHK
- 1
- Total units
- 155
- Buildings
- 2
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 125
- Land-owner share (not for sale)
- 30
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 122 | |
| 100% | 76% | 0% | – | |
| 100% | 29% | 0% | – | |
| 100% | 0% | 0% | 18 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400075
Projects with 70–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 3 yrs 8 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Feb 2027 | Mar 2028 |
| Concrete structure (RCC) | 100% | 88% |
| Units booked (free sale) | 98% | 74% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Divine Ultimus, Ghatkopar East
- Antariksh Alpha, Ghatkopar East
- Visava Harmony, Ghatkopar East
- Prime Vista Phase - 2, Ghatkopar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Divine Ultimus | June 2024 | December 2027 | 90% | 40 units booked out of 54 units for sale |
| Antariksh Alpha | February 2024 | June 2028 | 85% | 52 units booked out of 59 units for sale |
| Visava Harmony | August 2024 | March 2027 | 94% | – |
| Prime Vista Phase - 2 | August 2024 | June 2028 | 0% | 51 units booked out of 77 units for sale |
About this project
Aakruti Solitaire by Saptrishi Classic LLP is a 155-unit MHADA-sanctioned project in Ghatkopar East, Mumbai 400075, launched in May 2024 with possession due in February 2027. 122 units booked out of 125 units for sale. The concrete structure (RCC) is complete.
Read full summary
Aakruti Solitaire is a MHADA-sanctioned project by Saptrishi Classic LLP in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800056319. It was launched in May 2024. It has 155 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 155 units, 125 are for sale and 30 are the land-owner's share, not for sale.
Its registered possession date is February 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.
122 units booked out of 125 units for sale (98%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 76% to 100%.