Visava Harmony, Ghatkopar East

by Best Super Edge Construction LLP · Ghatkopar East, Mumbai 400075 · Map

Launched
Aug 20242 yrs 7 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
94%Mid-construction
Booked
–
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
62
2 BHK
33
Total units
95
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)94%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 65%Oct 2026: Concrete structure (RCC) 94%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 94%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%94%0%–
100%65%0%–
100%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400075

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400075
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 7 mths3 yrs 8 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Mar 2027Mar 2028
Concrete structure (RCC)94%88%
Units booked–81%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Visava Harmony by Best Super Edge Construction LLP is a 95-unit MHADA-sanctioned project in Ghatkopar East, Mumbai 400075, launched in August 2024 with possession due in March 2027. The concrete structure (RCC) is 94% complete.

Read full summary

Visava Harmony is a MHADA-sanctioned project by Best Super Edge Construction LLP in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800077296. It was launched in August 2024. It has 95 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 94% complete, final finishes not started.

Since the July 2026 update, the reported concrete structure (RCC) has gone from 65% to 94%.