Divine Ultimus, Ghatkopar East

by Shree Dham Developers · Ghatkopar East, Mumbai 400075 · Map

Launched
Jun 20243 yrs 6 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
90%Mid-construction
Booked (free sale)
40 of 5474% · 32 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale40 booked out of 54 units

Rehab32 units for existing members

Total 86 units. Rehab units are not for sale.

Project facts

1 BHK
26
2 BHK
43
3 BHK
17
Total units
86
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
54
Rehab units
32

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 90%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%10%40
100%0%0%31
100%0%0%23
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400075

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400075
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths2 yrs 8 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2027Mar 2027
Concrete structure (RCC)90%94%
Units booked (free sale)74%88%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Divine Ultimus by Shree Dham Developers is an 86-unit MHADA-sanctioned project in Ghatkopar East, Mumbai 400075, launched in June 2024 with possession due in December 2027. 40 units booked out of 54 units for sale. The concrete structure (RCC) is 90% complete.

Read full summary

Divine Ultimus is a MHADA-sanctioned project by Shree Dham Developers in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800076816. It was launched in June 2024. It has 86 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 86 units, 54 are for sale and 32 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes 10% complete.

40 units booked out of 54 units for sale (74%). Since the July 2026 update, 9 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 90%.