Airica, Bhandup West

by Jai Hind Oil Mills Company · Bhandup West, Mumbai 400078 · Map

Launched
Mar 2024First of 3 phases
Possession (MahaRERA)
Dec 2029 – Jun 2030Not extended
Concrete structure
19%Weighted across 3 phases
Booked
512 of 68475% · 516 in Jul 2026
Buildings
31.4 acres
MahaRERA complaints
6Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
70
2 BHK
381
3 BHK
125
4 BHK
65
Other units
43
Total units
684
Buildings
3
Land
1.4 acres
Phases
3
MahaRERA complaints
6

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Airica Tower 1
Mid-construction
P5180005512525921%68%
Airica Tower 4
Mid-construction
P5180005516624415%84%
Airica Tower 2
Mid-construction
P5180007775613824%72%
Show updates by phase

Airica Tower 1 (P51800055125)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%21%0%187
100%0%0%187
100%0%0%151
100%0%0%113

"–" means MahaRERA shows no figure for that update.

Airica Tower 4 (P51800055166)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%15%0%215
80%0%0%215
80%0%0%180
80%0%0%133

"–" means MahaRERA shows no figure for that update.

Airica Tower 2 (P51800077756)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%24%0%110
100%0%0%114
100%0%0%59
100%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)19%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 92%Dec 2025: Excavation 92%Jul 2026: Excavation 92%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 19%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 19%Final finishes 0%

How to read construction stages

Compared with 4 similar projects in PIN 400078

Projects with 300–1,300 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 9 mths5 yrs 6 mths
Possession date extendedNo2 of 4
Possession date (MahaRERA)Dec 2029 – Jun 2030Jan 2031
Concrete structure (RCC)19%6%
Units booked75%59%
MahaRERA complaints (filed by or against the builder)60

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Airica by Jai Hind Oil Mills Company is a 684-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, registered with MahaRERA in 3 phases, with possession dates from December 2029 to June 2030. 512 units booked out of total 684 units. The concrete structure (RCC) is 19% complete.

Read full summary

Airica is a BMC-sanctioned project by Jai Hind Oil Mills Company in Bhandup West, Mumbai 400078, registered with MahaRERA as 3 phases (P51800055125, P51800055166, P51800077756). The first phase was launched in March 2024. Together the phases have 684 units in 3 buildings: 641 homes (1, 2, 3 and 4 BHK) and 43 other units (shops, offices or not given by type), as registered with MahaRERA. All 3 phases are active on MahaRERA.

The phases' registered possession dates run from December 2029 to June 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 19% complete and final finishes 0% complete. None of the 3 phases has its structure complete.

512 units booked out of total 684 units (75%).