Raheja Antares, Bhandup West
by K Raheja Corp Real Estate Private Limited · Bhandup West, Mumbai 400078 · Map
- Launched
- Aug 2024First of 2 phases
- Possession (MahaRERA)
- Nov 2029Not extended
- Concrete structure
- 12%Weighted across 2 phases
- Booked
- 333 of 48569% · 306 in Jul 2026
- Buildings
- 21.7 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 86
- 3 BHK
- 165
- 4 BHK
- 52
- Other units
- 182
- Total units
- 485
- Buildings
- 2
- Land
- 1.7 acres
- Phases
- 2
- MahaRERA complaints
- 1
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Raheja Antares - Tower A Early stage | P51800077483 | 136 | 0% | 70% | |
| Raheja Antares - Tower B Mid-construction | P51800079836 | 167 | 21% | 68% |
Show updates by phase
Raheja Antares - Tower A (P51800077483)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 137 | |
| 100% | 0% | 0% | 136 | |
| 100% | 0% | 0% | 109 | |
| 41% | 0% | 0% | 86 |
"–" means MahaRERA shows no figure for that update.
Raheja Antares - Tower B (P51800079836)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 21% | 0% | 196 | |
| 100% | 3% | 0% | 170 | |
| 75% | 0% | 0% | 77 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 5 similar projects in PIN 400078
Projects with 150–700 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs | 5 yrs 8 mths |
| Possession date extended | No | 2 of 5 |
| Possession date (MahaRERA) | Nov 2029 | Dec 2029 |
| Concrete structure (RCC) | 12% | 39% |
| Units booked | 69% | 70% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 5 projects
- Vanita Sadan CHS, Bhandup West
- Arkade Rare, Bhandup West
- Godrej Nurture, Bhandup West
- Corinthia, Bhandup West
- Airica, Bhandup West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vanita Sadan CHS | August 2024 | December 2028 | 57% | 150 units booked out of 181 units for sale |
| Arkade Rare | August 2024 | December 2028 | 69% | 333 units booked out of total 479 units |
| Godrej Nurture | July 2024 | Mar 2032 – Jul 2032 | 0% | 310 units booked out of total 616 units |
| Corinthia | October 2024 | May 2031 – Nov 2031 | 39% | 346 units booked out of total 621 units |
| Airica | March 2024 | Dec 2029 – Jun 2030 | 19% | 512 units booked out of total 684 units |
About this project
Raheja Antares by K Raheja Corp Real Estate Private Limited is a 485-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, registered with MahaRERA in 2 phases, with possession due in November 2029. 333 units booked out of total 485 units. The concrete structure (RCC) is 12% complete.
Read full summary
Raheja Antares is a BMC-sanctioned project by K Raheja Corp Real Estate Private Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as 2 phases (P51800077483, P51800079836). The first phase was launched in August 2024. Together the phases have 485 units in 2 buildings: 303 homes (2, 3 and 4 BHK) and 182 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.
The registered possession date is November 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 12% complete and final finishes 0% complete. Neither phase has its structure complete.
333 units booked out of total 485 units (69%). Since the July 2026 update, 27 more units have been booked.
K Raheja Corp's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 12 |
|---|---|
| Total units across these projects | 1,377 |
| Completed without extending the possession date | 3 |
| Completed after an extension | 1 |
| Lapsed | 0 |
| Under construction | 8 |
| Possession date extended on the builder's application | 1 |
| Typical time from launch to 100% structure | 4 years 4 months |
| MahaRERA complaints (filed by or against the builder), all K Raheja Corp projects | 3 (3 of 12 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.