Godrej Nurture, Bhandup West

by Godrej Properties Limited · Bhandup West, Mumbai 400078 · Map

Launched
Jul 2024First of 2 phases
Possession (MahaRERA)
Mar 2032 – Jul 2032Extended in both phases
Concrete structure
0%Weighted across 2 phases
Booked
310 of 61650% · 251 in Jul 2026
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
467
3 BHK
149
Total units
616
Buildings
2
Land
0.3 acres
Phases
2
MahaRERA complaints
0

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Godrej Nurture - Tower 2
Early stage
P518000770803030%44%
Godrej Nurture - Tower 3
Early stage
P518000770853130%56%
Show updates by phase

Godrej Nurture - Tower 2 (P51800077080)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
5%0%0%134
5%0%0%112
5%0%0%92
5%0%0%68

"–" means MahaRERA shows no figure for that update.

Godrej Nurture - Tower 3 (P51800077085)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
5%0%0%176
5%0%0%139
5%0%0%93
5%0%0%50

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation5%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 5%Dec 2025: Excavation 5%Jul 2026: Excavation 5%Oct 2026: Excavation 5%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 5%Concrete structure (RCC) 0%Final finishes 0%

How to read construction stages

Compared with 5 similar projects in PIN 400078

Projects with 300–1,300 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 8 mths5 yrs 8 mths
Possession date extendedYes2 of 5
Possession date (MahaRERA)Mar 2032 – Jul 2032Dec 2029
Concrete structure (RCC)0%19%
Units booked50%69%
MahaRERA complaints (filed by or against the builder)01

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Godrej Nurture by Godrej Properties Limited is a 616-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, registered with MahaRERA in 2 phases, with possession dates from March 2032 to July 2032. 310 units booked out of total 616 units. Work on the concrete structure (RCC) has not started.

Read full summary

Godrej Nurture is a BMC-sanctioned project by Godrej Properties Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as 2 phases (P51800077080, P51800077085). The first phase was launched in July 2024. Together the phases have 616 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Both phases are active on MahaRERA.

The phases' registered possession dates run from March 2032 to July 2032; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 0% complete and final finishes 0% complete. Neither phase has its structure complete.

310 units booked out of total 616 units (50%). Since the July 2026 update, 59 more units have been booked.

Godrej's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA35
Total units across these projects10,289
Completed without extending the possession date9
Completed after an extension0
Lapsed2
Under construction24
Possession date extended on the builder's application5
Typical time from launch to 100% structure6 years 3 months
MahaRERA complaints (filed by or against the builder), all Godrej projects86 (17 of 35 projects)