by Arkade Developers Limited · Bhandup West, Mumbai 400078 · Map

Launched
Aug 20244 yrs 4 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
69%Mid-construction
Booked
333 of 47970% · 290 in Jul 2026
Buildings
73 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
366
3 BHK
66
Other units
47
Total units
479
Buildings
7
Land
3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)69%
Finishes, lifts and services21%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 99%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 57%Oct 2026: Concrete structure (RCC) 69%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 2%Oct 2026: Final finishes 21%Excavation 100%Concrete structure (RCC) 69%Final finishes 21%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%69%21%333
100%57%2%290
100%10%0%162
99%0%0%68

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400078

Projects with 200–900 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 4 mths5 yrs 8 mths
Possession date extendedNo2 of 5
Possession date (MahaRERA)Dec 2028Dec 2029
Concrete structure (RCC)69%19%
Units booked70%69%
MahaRERA complaints (filed by or against the builder)01

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Arkade Rare by Arkade Developers Limited is a 479-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, launched in August 2024 with possession due in December 2028. 333 units booked out of total 479 units. The concrete structure (RCC) is 69% complete.

Read full summary

Arkade Rare is a BMC-sanctioned project by Arkade Developers Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800077307. It was launched in August 2024. It has 479 units in 7 buildings: 432 homes (2 and 3 BHK) and 47 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 69% complete, final finishes 21% complete.

333 units booked out of total 479 units (70%). Since the July 2026 update, 43 more units have been booked and the reported concrete structure (RCC) has gone from 57% to 69%.

Arkade's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA27
Total units across these projects3,356
Completed without extending the possession date14
Completed after an extension0
Lapsed3
Under construction10
Possession date extended on the builder's application1
Typical time from launch to 100% structure3 years 8 months
MahaRERA complaints (filed by or against the builder), all Arkade projects15 (6 of 27 projects)

See all Arkade projects →