Moti Niwas, Vile Parle East
by Jls Builders& Developers LLP · Vile Parle East, Mumbai 400057 · Map
- Launched
- Apr 20243 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 23%Mid-construction
- Booked (free sale)
- 2 of 729% · 29 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale2 booked out of 7 units
Rehab29 units for existing members
Total 36 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 12
- 2 BHK
- 13
- 3 BHK
- 1
- Other units
- 10
- Total units
- 36
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 7
- Rehab units
- 29
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 23% | 0% | 2 | |
| 100% | 0% | 0% | 2 | |
| 70% | 0% | 0% | 2 | |
| 70% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400057
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 8 mths | 2 yrs 4 mths |
| Possession date extended | No | 3 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2026 |
| Concrete structure (RCC) | 23% | 100% |
| Units booked (free sale) | 29% | 48% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Moti Madhav, Vile Parle East
- Ganga Niwas Chs Ltd, Vile Parle East
- Ridhi Sidhi Sadan Of Ridhi Sidhi Co Operative Housing Society Ltd, Vile Parle East
- Shri Sai Krupa, Vile Parle East
- Yeshwant Sadan, Vile Parle East
- Vanmala Nivas Chs Ltd, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Moti Madhav | April 2024 | September 2026 | 100% | 3 units booked out of 6 units for sale |
| Ganga Niwas Chs Ltd | April 2024 | December 2029 | 100% | 9 units booked out of 16 units for sale |
| Ridhi Sidhi Sadan Of Ridhi Sidhi Co Operative Housing Society Ltd | April 2024 | June 2028 | 100% | 7 units booked out of 21 units for sale |
| Shri Sai Krupa | May 2024 | January 2027 | 100% | 2 units booked out of 8 units for sale |
| Yeshwant Sadan | May 2024 | September 2026 | 100% | 5 units booked out of 11 units for sale |
| Vanmala Nivas Chs Ltd | June 2024 | November 2026 | 100% | 6 units booked out of 10 units for sale |
About this project
Moti Niwas by Jls Builders& Developers LLP is a 36-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in April 2024 with possession due in December 2027. 2 units booked out of 7 units for sale. The concrete structure (RCC) is 23% complete.
Read full summary
Moti Niwas is a BMC-sanctioned project by Jls Builders& Developers LLP in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800055679. It was launched in April 2024. It has 36 units in 1 building: 26 homes (1, 2 and 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 36 units, 7 are for sale and 29 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 23% complete, final finishes not started.
2 units booked out of 7 units for sale (29%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 23%.