Vanmala Nivas Chs Ltd, Vile Parle East
by Ami Infra Realtors · Vile Parle East, Mumbai 400057 · Map
- Launched
- Jun 20241 yr 6 mths originally promised
- Possession (MahaRERA)
- Nov 2026Extended by 11 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 6 of 1060% · 10 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale6 booked out of 10 units
Rehab10 units for existing members
Total 20 units. Rehab units are not for sale.
Project facts
- 1 RK
- 5
- 1 BHK
- 5
- 2 BHK
- 5
- 3 BHK
- 4
- Other units
- 1
- Total units
- 20
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 10
- Rehab units
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 70% | 6 | |
| 100% | 50% | 0% | 3 | |
| 100% | 25% | 0% | 2 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400057
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 6 mths | 2 yrs 3 mths |
| Possession date extended | By 11 mths | 2 of 6 |
| Possession date (MahaRERA) | Nov 2026 | Nov 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 60% | 39% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Yeshwant Sadan, Vile Parle East
- Shri Sai Krupa, Vile Parle East
- Vaastu Shreya, Vile Parle East
- Regent Aparna Mahal, Vile Parle East
- Moti Niwas, Vile Parle East
- Moti Madhav, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Yeshwant Sadan | May 2024 | September 2026 | 100% | 5 units booked out of 11 units for sale |
| Shri Sai Krupa | May 2024 | January 2027 | 100% | 2 units booked out of 8 units for sale |
| Vaastu Shreya | July 2024 | May 2026 | 100% | 7 units booked out of total 8 units |
| Regent Aparna Mahal | August 2024 | March 2027 | 100% | 3 units booked out of 9 units for sale |
| Moti Niwas | April 2024 | December 2027 | 23% | 2 units booked out of 7 units for sale |
| Moti Madhav | April 2024 | September 2026 | 100% | 3 units booked out of 6 units for sale |
About this project
Vanmala Nivas Chs Ltd by Ami Infra Realtors is a 20-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in June 2024 with possession due in November 2026. 6 units booked out of 10 units for sale. The concrete structure (RCC) is complete.
Read full summary
Vanmala Nivas Chs Ltd is a BMC-sanctioned project by Ami Infra Realtors in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800076696. It was launched in June 2024. It has 20 units in 1 building: 19 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 20 units, 10 are for sale and 10 are rehab units for existing members.
Its registered possession date is November 2026, extended by 11 months from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.
6 units booked out of 10 units for sale (60%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 50% to 100%.