Shri Sai Krupa, Vile Parle East

by Arham Realty · Vile Parle East, Mumbai 400057 · Map

Launched
May 20242 yrs 8 mths promised
Possession (MahaRERA)
Jan 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
2 of 825% · 16 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale2 booked out of 8 units

Rehab16 units for existing members

Total 24 units. Rehab units are not for sale.

Project facts

1 RK
2
1 BHK
1
2 BHK
7
3 BHK
12
4 BHK
2
Total units
24
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
8
Rehab units
16

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services40%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 40%Oct 2026: Final finishes 40%Excavation 100%Concrete structure (RCC) 100%Final finishes 40%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%40%2
100%100%40%2
100%90%0%2
100%90%0%1

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 8 mths2 yrs 3 mths
Possession date extendedNo3 of 6
Possession date (MahaRERA)Jan 2027Jan 2027
Concrete structure (RCC)100%100%
Units booked (free sale)25%48%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shri Sai Krupa by Arham Realty is a 24-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in May 2024 with possession due in January 2027. 2 units booked out of 8 units for sale. The concrete structure (RCC) is complete.

Read full summary

Shri Sai Krupa is a BMC-sanctioned project by Arham Realty in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800056283. It was launched in May 2024. It has 24 units in 1 building, with 1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 24 units, 8 are for sale and 16 are rehab units for existing members.

Its registered possession date is January 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 40% complete.

2 units booked out of 8 units for sale (25%).