Yeshwant Sadan, Vile Parle East
Ready to moveLapsed
by Arg Life Spaces LLP · Vile Parle East, Mumbai 400057 · Map
- Launched
- May 20241 yr 7 mths originally promised
- Possession (MahaRERA)
- Sep 2026Extended by 9 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 5 of 1145% · 5 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale5 booked out of 11 units
Rehab5 units for existing members
Land-owner share4 units, not for sale
Total 20 units. Rehab and land-owner units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 2
- 2 BHK
- 8
- 3 BHK
- 6
- 4 BHK
- 2
- Other units
- 1
- Total units
- 20
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 11
- Rehab units
- 5
- Land-owner share (not for sale)
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 5 | |
| 100% | 90% | 50% | 5 | |
| 100% | 90% | 20% | 4 | |
| 100% | 60% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400057
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 7 mths | 2 yrs 3 mths |
| Possession date extended | By 9 mths | 2 of 6 |
| Possession date (MahaRERA) | Sep 2026 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 45% | 42% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Shri Sai Krupa, Vile Parle East
- Vanmala Nivas Chs Ltd, Vile Parle East
- Moti Niwas, Vile Parle East
- Moti Madhav, Vile Parle East
- Vaastu Shreya, Vile Parle East
- Regent Aparna Mahal, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shri Sai Krupa | May 2024 | January 2027 | 100% | 2 units booked out of 8 units for sale |
| Vanmala Nivas Chs Ltd | June 2024 | November 2026 | 100% | 6 units booked out of 10 units for sale |
| Moti Niwas | April 2024 | December 2027 | 23% | 2 units booked out of 7 units for sale |
| Moti Madhav | April 2024 | September 2026 | 100% | 3 units booked out of 6 units for sale |
| Vaastu Shreya | July 2024 | May 2026 | 100% | 7 units booked out of total 8 units |
| Regent Aparna Mahal | August 2024 | March 2027 | 100% | 3 units booked out of 9 units for sale |
About this project
Yeshwant Sadan by Arg Life Spaces LLP is a 20-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in May 2024; its MahaRERA registration has lapsed. 5 units booked out of 11 units for sale. The concrete structure (RCC) is complete.
Read full summary
Yeshwant Sadan is a BMC-sanctioned project by Arg Life Spaces LLP in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800056424. It was launched in May 2024. It has 20 units in 1 building: 19 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 20 units, 11 are for sale, 5 are rehab units for existing members and 4 are the land-owner's share, not for sale.
Possession was due in September 2026, after an extension of 9 months from the original December 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
5 units booked out of 11 units for sale (45%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 90% to 100%.