Shiv Krupa, Borivali East
by M/s. J. V. Constructions & Developers · Borivali East, Mumbai 400066 · Map
- Launched
- May 20244 yrs 7 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 25%Mid-construction
- Booked (free sale)
- 39 of 8049% · 43 rehab units
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale39 booked out of 80 units
Rehab43 units for existing members
Total 123 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 96
- 2 BHK
- 11
- Other units
- 16
- Total units
- 123
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 80
- Rehab units
- 43
- Reserved units
- 15
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 25% | 0% | 39 | |
| 100% | 25% | 0% | 24 | |
| 100% | 0% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400066
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 7 mths | 3 yrs 1 mth |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | Dec 2028 | May 2027 |
| Concrete structure (RCC) | 25% | 100% |
| Units booked (free sale) | 49% | 83% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Anand Co-Operative Housing Society Ltd Building No 2, Borivali East
- Borivali Shiv Sadan CHSL, Borivali East
- Balaji Heights Redevelopment Of Rajendra Nagar Om Sairam Chs Ltd, Borivali East
- Samarpan Sankalp, Borivali East
- Nl Park View, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Anand Co-Operative Housing Society Ltd Building No 2 | April 2024 | December 2026 | 38% | 15 units booked out of 41 units for sale |
| Borivali Shiv Sadan CHSL | June 2024 | October 2027 | 100% | 65 units booked out of 66 units for sale |
| Balaji Heights Redevelopment Of Rajendra Nagar Om Sairam Chs Ltd | April 2024 | May 2027 | 12% | 59 units booked out of 162 units for sale |
| Samarpan Sankalp | February 2024 | December 2026 | 100% | 66 units booked out of 72 units for sale |
| Nl Park View | August 2024 | May 2028 | 100% | 34 units booked out of 41 units for sale |
About this project
Shiv Krupa by M/s. J. V. Constructions & Developers is a 123-unit SRA-sanctioned project in Borivali East, Mumbai 400066, launched in May 2024 with possession due in December 2028. 39 units booked out of 80 units for sale. The concrete structure (RCC) is 25% complete.
Read full summary
Shiv Krupa is an SRA-sanctioned project by M/s. J. V. Constructions & Developers in Borivali East, Mumbai 400066, registered with MahaRERA as P51800056181. It was launched in May 2024. It has 123 units in 2 buildings: 107 homes (1 and 2 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 123 units, 80 are for sale and 43 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 25% complete, final finishes not started.
39 units booked out of 80 units for sale (49%). Since the July 2026 update, 15 more units have been booked.