Skip to main content

Triguni Heights, Borivali West

by Triguni Builders & Developers Pvt Ltd · Borivali West, Mumbai 400092 · Map

Launched
Jan 20252 yrs 11 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
70%Mid-construction
Booked (free sale)
0 of 350% · 56 rehab units
Buildings
20.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 35 units

Rehab56 units for existing members

Total 91 units. Rehab units are not for sale.

Project facts

1 BHK
35
2 BHK
41
3 BHK
15
Total units
91
Buildings
2
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
35
Rehab units
56

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)70%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 70%Oct 2026: Concrete structure (RCC) 70%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 70%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%0%0
100%70%0%0
100%0%0%0
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 11 mths3 yrs 9 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2027Nov 2028
Concrete structure (RCC)70%63%
Units booked (free sale)0%43%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Triguni Heights by Triguni Builders & Developers Pvt Ltd is a 91-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in January 2025 with possession due in December 2027. 0 units booked out of 35 units for sale. The concrete structure (RCC) is 70% complete.

Read full summary

Triguni Heights is a BMC-sanctioned project by Triguni Builders & Developers Pvt Ltd in Borivali West, Mumbai 400092, registered with MahaRERA as P51800078674. It was launched in January 2025. It has 91 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 91 units, 35 are for sale and 56 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.

0 units booked out of 35 units for sale (0%).