Skip to main content

Zen Pristine, Borivali West

by Konark Shakti Group Of Company · Borivali West, Mumbai 400092 · Map

Launched
Jan 20253 yrs 11 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
30%Mid-construction
Booked (free sale)
10 of 3330% · 29 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale10 booked out of 33 units

Rehab29 units for existing members

Total 62 units. Rehab units are not for sale.

Project facts

1 BHK
12
2 BHK
28
3 BHK
7
Other units
15
Total units
62
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
33
Rehab units
29

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)30%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 30%Jul 2026: Concrete structure (RCC) 30%Oct 2026: Concrete structure (RCC) 30%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 30%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%30%0%10
100%30%0%10
100%30%0%10
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 11 mths3 yrs 3 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028May 2028
Concrete structure (RCC)30%71%
Units booked (free sale)30%37%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Zen Pristine by Konark Shakti Group Of Company is a 62-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in January 2025 with possession due in December 2028. 10 units booked out of 33 units for sale. The concrete structure (RCC) is 30% complete.

Read full summary

Zen Pristine is a BMC-sanctioned project by Konark Shakti Group Of Company in Borivali West, Mumbai 400092, registered with MahaRERA as P51800078892. It was launched in January 2025. It has 62 units in 1 building: 47 homes (1, 2 and 3 BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 62 units, 33 are for sale and 29 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 30% complete, final finishes not started.

10 units booked out of 33 units for sale (30%).