Sayba Samriddhi, Chembur

by Shanaya Star · Chembur, Mumbai 400071 · Map

Launched
Dec 20242 yrs 6 mths promised
Possession (MahaRERA)
Jun 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
80 of 8990% · 36 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale80 booked out of 89 units

Rehab36 units for existing members

Total 125 units. Rehab units are not for sale.

Project facts

1 BHK
16
2 BHK
108
3 BHK
1
Total units
125
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
89
Rehab units
36

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 59%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%80
100%100%0%55
100%59%0%24
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 60–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 6 mths3 yrs 11 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jun 2027Dec 2028
Concrete structure (RCC)100%58%
Units booked (free sale)90%52%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Sayba Samriddhi by Shanaya Star is a 125-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in December 2024 with possession due in June 2027. 80 units booked out of 89 units for sale. The concrete structure (RCC) is complete.

Read full summary

Sayba Samriddhi is a MHADA-sanctioned project by Shanaya Star in Chembur, Mumbai 400071, registered with MahaRERA as P51800078403. It was launched in December 2024. It has 125 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 125 units, 89 are for sale and 36 are rehab units for existing members.

Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

80 units booked out of 89 units for sale (90%). Since the July 2026 update, 25 more units have been booked.