Skip to main content

Adityaraj Springs, Chembur

by Adityaraj Lifestyle · Chembur, Mumbai 400071 · Map

Launched
Feb 20253 yrs 10 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
70%Mid-construction
Booked (free sale)
60 of 12847% · 33 rehab units
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale60 booked out of 128 units

Rehab33 units for existing members

Total 161 units. Rehab units are not for sale.

Project facts

1 BHK
103
2 BHK
46
Other units
12
Total units
161
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
128
Rehab units
33

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)70%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 45%Oct 2026: Concrete structure (RCC) 70%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 70%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%0%60
100%45%0%–
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 70–300 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths3 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028Dec 2028
Concrete structure (RCC)70%50%
Units booked (free sale)47%76%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Adityaraj Springs by Adityaraj Lifestyle is a 161-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in February 2025 with possession due in December 2028. 60 units booked out of 128 units for sale. The concrete structure (RCC) is 70% complete.

Read full summary

Adityaraj Springs is a MHADA-sanctioned project by Adityaraj Lifestyle in Chembur, Mumbai 400071, registered with MahaRERA as P51800079352. It was launched in February 2025. It has 161 units in 2 buildings: 149 homes (1 and 2 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 161 units, 128 are for sale and 33 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.

60 units booked out of 128 units for sale (47%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 45% to 70%.

Adityaraj's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA29
Total units across these projects3,149
Completed without extending the possession date7
Completed after an extension2
Lapsed10
Under construction10
Possession date extended on the builder's application2
Typical time from launch to 100% structure3 years 6 months
MahaRERA complaints (filed by or against the builder), all Adityaraj projects2 (2 of 29 projects)

See all Adityaraj projects →