Skip to main content

Vighnaharta Enclave, Chembur

by Vighnaharta Heights Private Limited · Chembur, Mumbai 400071 · Map

Launched
Mar 20253 yrs 9 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
45 of 13434% · 24 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale45 booked out of 134 units

Rehab24 units for existing members

Total 158 units. Rehab units are not for sale.

Project facts

1 RK
3
1 BHK
109
2 BHK
46
Total units
158
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
134
Rehab units
24
Reserved units
32

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%45
100%0%0%32
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 70–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths3 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028Dec 2028
Concrete structure (RCC)0%85%
Units booked (free sale)34%54%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Vighnaharta Enclave by Vighnaharta Heights Private Limited is a 158-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in March 2025 with possession due in December 2028. 45 units booked out of 134 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Vighnaharta Enclave is a MHADA-sanctioned project by Vighnaharta Heights Private Limited in Chembur, Mumbai 400071, registered with MahaRERA as P51800079459. It was launched in March 2025. It has 158 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 158 units, 134 are for sale and 24 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

45 units booked out of 134 units for sale (34%). Since the July 2026 update, 13 more units have been booked.