Adityaraj Platinum, Chembur

by Adityaraj Housing Company · Chembur, Mumbai 400071 · Map

Launched
Dec 20243 yrs 8 mths promised
Possession (MahaRERA)
Aug 2028Not extended
Concrete structure
47%Mid-construction
Booked (free sale)
54 of 9457%
Buildings
20.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale54 booked out of 94 units

Land-owner share30 units, not for sale

Total 124 units. Land-owner units are not for sale.

Project facts

1 BHK
32
2 BHK
32
Other units
60
Total units
124
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
94
Land-owner share (not for sale)
30

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)47%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 47%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 47%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%47%0%54
0%0%0%0
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths3 yrs 11 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Aug 2028Dec 2028
Concrete structure (RCC)47%84%
Units booked (free sale)57%65%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Adityaraj Platinum by Adityaraj Housing Company is a 124-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in December 2024 with possession due in August 2028. 54 units booked out of 94 units for sale. The concrete structure (RCC) is 47% complete.

Read full summary

Adityaraj Platinum is a MHADA-sanctioned project by Adityaraj Housing Company in Chembur, Mumbai 400071, registered with MahaRERA as P51800078606. It was launched in December 2024. It has 124 units in 2 buildings: 64 homes (1 and 2 BHK) and 60 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 124 units, 94 are for sale and 30 are the land-owner's share, not for sale.

Its registered possession date is August 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 47% complete, final finishes not started.

54 units booked out of 94 units for sale (57%). Since the July 2026 update, 54 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 47%.

Adityaraj's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA29
Total units across these projects3,149
Completed without extending the possession date7
Completed after an extension2
Lapsed10
Under construction10
Possession date extended on the builder's application2
Typical time from launch to 100% structure3 years 6 months
MahaRERA complaints (filed by or against the builder), all Adityaraj projects2 (2 of 29 projects)