Adityaraj Platinum, Chembur
by Adityaraj Housing Company · Chembur, Mumbai 400071 · Map
- Launched
- Dec 20243 yrs 8 mths promised
- Possession (MahaRERA)
- Aug 2028Not extended
- Concrete structure
- 47%Mid-construction
- Booked (free sale)
- 54 of 9457%
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale54 booked out of 94 units
Land-owner share30 units, not for sale
Total 124 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 32
- 2 BHK
- 32
- Other units
- 60
- Total units
- 124
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 94
- Land-owner share (not for sale)
- 30
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 47% | 0% | 54 | |
| 0% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400071
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 8 mths | 3 yrs 11 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Aug 2028 | Dec 2028 |
| Concrete structure (RCC) | 47% | 84% |
| Units booked (free sale) | 57% | 65% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Raghav Vista, Chembur
- Sayba Samriddhi, Chembur
- Atharva Vaibhav, Chembur
- Trigun, Chembur
- Chembur White House CHS Ltd, Chembur
- Swastik Legacy, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Raghav Vista | December 2024 | December 2028 | 100% | 60 units booked out of 71 units for sale |
| Sayba Samriddhi | December 2024 | June 2027 | 100% | 80 units booked out of 89 units for sale |
| Atharva Vaibhav | December 2024 | December 2028 | 0% | 89 units booked out of 92 units for sale |
| Trigun | January 2025 | November 2027 | 100% | 4 units booked out of 22 units for sale |
| Chembur White House CHS Ltd | November 2024 | December 2028 | 69% | 40 units booked out of 90 units for sale |
| Swastik Legacy | February 2025 | December 2028 | 0% | 53 units booked out of total 116 units |
About this project
Adityaraj Platinum by Adityaraj Housing Company is a 124-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in December 2024 with possession due in August 2028. 54 units booked out of 94 units for sale. The concrete structure (RCC) is 47% complete.
Read full summary
Adityaraj Platinum is a MHADA-sanctioned project by Adityaraj Housing Company in Chembur, Mumbai 400071, registered with MahaRERA as P51800078606. It was launched in December 2024. It has 124 units in 2 buildings: 64 homes (1 and 2 BHK) and 60 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 124 units, 94 are for sale and 30 are the land-owner's share, not for sale.
Its registered possession date is August 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 47% complete, final finishes not started.
54 units booked out of 94 units for sale (57%). Since the July 2026 update, 54 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 47%.
Adityaraj's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 29 |
|---|---|
| Total units across these projects | 3,149 |
| Completed without extending the possession date | 7 |
| Completed after an extension | 2 |
| Lapsed | 10 |
| Under construction | 10 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 3 years 6 months |
| MahaRERA complaints (filed by or against the builder), all Adityaraj projects | 2 (2 of 29 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.