Trigun, Chembur

by National Properties · Chembur, Mumbai 400071 · Map

Launched
Jan 20252 yrs 10 mths promised
Possession (MahaRERA)
Nov 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
4 of 2218% · 12 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 22 units

Rehab12 units for existing members

Total 34 units. Rehab units are not for sale.

Project facts

2 BHK
11
3 BHK
23
Total units
34
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
22
Rehab units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 69%Jul 2026: Concrete structure (RCC) 92%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%4
100%92%0%4
100%69%0%4

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths3 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Nov 2027Jul 2028
Concrete structure (RCC)100%82%
Units booked (free sale)18%56%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Trigun by National Properties is a 34-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in January 2025 with possession due in November 2027. 4 units booked out of 22 units for sale. The concrete structure (RCC) is complete.

Read full summary

Trigun is a BMC-sanctioned project by National Properties in Chembur, Mumbai 400071, registered with MahaRERA as P51800078981. It was launched in January 2025. It has 34 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 34 units, 22 are for sale and 12 are rehab units for existing members.

Its registered possession date is November 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

4 units booked out of 22 units for sale (18%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 92% to 100%.