Skip to main content

Pardis Chitragandha, Chembur

by Pardis Construction LLP · Chembur, Mumbai 400071 · Map

Launched
Jan 20253 yrs 11 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
77%Mid-construction
Booked (free sale)
3 of 1127% · 12 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale3 booked out of 11 units

Rehab12 units for existing members

Total 23 units. Rehab units are not for sale.

Project facts

1 BHK
6
2 BHK
13
3 BHK
4
Total units
23
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
11
Rehab units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)77%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 35%Oct 2026: Concrete structure (RCC) 77%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 77%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%77%0%3
100%35%0%3
100%0%0%3
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 11 mths3 yrs
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028Mar 2028
Concrete structure (RCC)77%95%
Units booked (free sale)27%52%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Pardis Chitragandha by Pardis Construction LLP is a 23-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in January 2025 with possession due in December 2028. 3 units booked out of 11 units for sale. The concrete structure (RCC) is 77% complete.

Read full summary

Pardis Chitragandha is a BMC-sanctioned project by Pardis Construction LLP in Chembur, Mumbai 400071, registered with MahaRERA as P51800078846. It was launched in January 2025. It has 23 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 23 units, 11 are for sale and 12 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 77% complete, final finishes not started.

3 units booked out of 11 units for sale (27%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 35% to 77%.