Aayush Gokul, Chembur
by Aayush Developers · Chembur, Mumbai 400071 · Map
- Launched
- Mar 20252 yrs 3 mths promised
- Possession (MahaRERA)
- Jun 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 19 of 2286% · 12 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale19 booked out of 22 units
Rehab12 units for existing members
Total 34 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 17
- 2 BHK
- 5
- 3 BHK
- 6
- 4 BHK
- 6
- Total units
- 34
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 22
- Rehab units
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 19 | |
| 100% | 70% | 0% | 9 | |
| 0% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400071
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 3 mths | 3 yrs 2 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Jun 2027 | Jun 2028 |
| Concrete structure (RCC) | 100% | 92% |
| Units booked (free sale) | 86% | 28% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Narulla, Chembur
- Sidhivinayak Aura, Chembur
- Kedarnath, Chembur
- Trigun, Chembur
- The Harvest, Chembur
- Pardis Chitragandha, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Narulla | March 2025 | June 2028 | 100% | 2 units booked out of 16 units for sale |
| Sidhivinayak Aura | March 2025 | December 2027 | 85% | 15 units booked out of 20 units for sale |
| Kedarnath | February 2025 | December 2028 | 80% | 7 units booked out of 13 units for sale |
| Trigun | January 2025 | November 2027 | 100% | 4 units booked out of 22 units for sale |
| The Harvest | May 2025 | June 2028 | 100% | 5 units booked out of 17 units for sale |
| Pardis Chitragandha | January 2025 | December 2028 | 77% | 3 units booked out of 11 units for sale |
About this project
Aayush Gokul by Aayush Developers is a 34-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in March 2025 with possession due in June 2027. 19 units booked out of 22 units for sale. The concrete structure (RCC) is complete.
Read full summary
Aayush Gokul is a BMC-sanctioned project by Aayush Developers in Chembur, Mumbai 400071, registered with MahaRERA as P51800079889. It was launched in March 2025. It has 34 units in 1 building, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 34 units, 22 are for sale and 12 are rehab units for existing members.
Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.
19 units booked out of 22 units for sale (86%). Since the July 2026 update, 10 more units have been booked and the reported concrete structure (RCC) has gone from 70% to 100%.