Manglam Rajanigandha, Borivali West
by Manglam & Karnani Ventures LLP · Borivali West, Mumbai 400092 · Map
- Launched
- Mar 20252 yrs 3 mths promised
- Possession (MahaRERA)
- Jun 2027Not extended
- Concrete structure
- 89%Mid-construction
- Booked (free sale)
- 10 of 3429% · 40 rehab units
- Buildings
- 30.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale10 booked out of 34 units
Rehab40 units for existing members
Total 74 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 68
- 3 BHK
- 6
- Total units
- 74
- Buildings
- 3
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 34
- Rehab units
- 40
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 89% | 15% | 10 | |
| 100% | 89% | 0% | 3 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400092
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 3 mths | 3 yrs 6 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Jun 2027 | Aug 2028 |
| Concrete structure (RCC) | 89% | 58% |
| Units booked (free sale) | 29% | 37% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Dotom Vue, Borivali West
- Vijaydeep, Borivali West
- Ruparel Zinnia, Borivali West
- Triguni Heights, Borivali West
- Zen Pristine, Borivali West
- Aafcon Harmony, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Dotom Vue | March 2025 | October 2028 | 45% | 47 units booked out of 84 units for sale |
| Vijaydeep | March 2025 | December 2027 | 72% | 7 units booked out of 16 units for sale |
| Ruparel Zinnia | February 2025 | June 2028 | 81% | 108 units booked out of total 133 units |
| Triguni Heights | January 2025 | December 2027 | 70% | 0 units booked out of 35 units for sale |
| Zen Pristine | January 2025 | December 2028 | 30% | 10 units booked out of 33 units for sale |
| Aafcon Harmony | July 2025 | December 2029 | 5% | 0 units booked out of 11 units for sale |
About this project
Manglam Rajanigandha by Manglam & Karnani Ventures LLP is a 74-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in March 2025 with possession due in June 2027. 10 units booked out of 34 units for sale. The concrete structure (RCC) is 89% complete.
Read full summary
Manglam Rajanigandha is a BMC-sanctioned project by Manglam & Karnani Ventures LLP in Borivali West, Mumbai 400092, registered with MahaRERA as P51800079800. It was launched in March 2025. It has 74 units in 3 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 74 units, 34 are for sale and 40 are rehab units for existing members.
Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 89% complete, final finishes 15% complete.
10 units booked out of 34 units for sale (29%). Since the July 2026 update, 7 more units have been booked.