Skip to main content

Gayatri Enclave, Andheri West

by Tawakkal Infra Projects Private Limited · Andheri West, Mumbai 400053 · Map

Launched
Feb 20254 yrs 10 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
50%Mid-construction
Booked (free sale)
5 of 4711% · 18 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 47 units

Rehab18 units for existing members

Total 65 units. Rehab units are not for sale.

Project facts

1 BHK
25
2 BHK
29
3 BHK
11
Total units
65
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
47
Rehab units
18

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)50%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 45%Oct 2026: Concrete structure (RCC) 50%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 50%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%0%5
100%45%0%0
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400053

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400053
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 10 mths3 yrs 11 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2029Dec 2028
Concrete structure (RCC)50%30%
Units booked (free sale)11%35%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Gayatri Enclave by Tawakkal Infra Projects Private Limited is a 65-unit SRA-sanctioned project in Andheri West, Mumbai 400053, launched in February 2025 with possession due in December 2029. 5 units booked out of 47 units for sale. The concrete structure (RCC) is 50% complete.

Read full summary

Gayatri Enclave is an SRA-sanctioned project by Tawakkal Infra Projects Private Limited in Andheri West, Mumbai 400053, registered with MahaRERA as P51800079275. It was launched in February 2025. It has 65 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 65 units, 47 are for sale and 18 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.

5 units booked out of 47 units for sale (11%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 45% to 50%.